From: Daniel on
Hello,
Usually Units = Work / Duration, but in some case it seems this formula
doesn't work.
I performed some basic tests in project:
First test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
Remaining work =5d
I changed Rem Work from 5d to 6d, the task become
Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is fine.

Second test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d and
Remaining work=4d
I changed Rem Work from 4d to 5d, the task become
Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work =5d
Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)

From: Jan De Messemaeker on
Hi Daniel,

Additional remaining work is spread out ofver the 4 days of remaining
duration (what's done is done)
So during those 4 days units are 125% (5/4)
And Units always show the MAXIMUM, not the AVERAGE

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Daniel" <daniel(a)discussions.microsoft.com.> wrote in message
news:E0787461-0F79-4777-84C9-3DF6D4E181AC(a)microsoft.com...
> Hello,
> Usually Units = Work / Duration, but in some case it seems this formula
> doesn't work.
> I performed some basic tests in project:
> First test: I created a fixed duration task:
> 1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
> Remaining work =5d
> I changed Rem Work from 5d to 6d, the task become
> Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is
> fine.
>
> Second test: I created a fixed duration task:
> 1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d and
> Remaining work=4d
> I changed Rem Work from 4d to 5d, the task become
> Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work =5d
> Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)
>


From: Daniel on
Thanks Jan.

"Jan De Messemaeker" wrote:

> Hi Daniel,
>
> Additional remaining work is spread out ofver the 4 days of remaining
> duration (what's done is done)
> So during those 4 days units are 125% (5/4)
> And Units always show the MAXIMUM, not the AVERAGE
>
> Hope this helps,
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Daniel" <daniel(a)discussions.microsoft.com.> wrote in message
> news:E0787461-0F79-4777-84C9-3DF6D4E181AC(a)microsoft.com...
> > Hello,
> > Usually Units = Work / Duration, but in some case it seems this formula
> > doesn't work.
> > I performed some basic tests in project:
> > First test: I created a fixed duration task:
> > 1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
> > Remaining work =5d
> > I changed Rem Work from 5d to 6d, the task become
> > Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is
> > fine.
> >
> > Second test: I created a fixed duration task:
> > 1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d and
> > Remaining work=4d
> > I changed Rem Work from 4d to 5d, the task become
> > Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work =5d
> > Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)
> >
>
>
> .
>
From: Jan De Messemaeker on
You're very welcome, Daniel

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Daniel" <daniel(a)discussions.microsoft.com.> wrote in message
news:E50AFDFB-ACCD-4034-9E16-6DA6CB817AB6(a)microsoft.com...
> Thanks Jan.
>
> "Jan De Messemaeker" wrote:
>
>> Hi Daniel,
>>
>> Additional remaining work is spread out ofver the 4 days of remaining
>> duration (what's done is done)
>> So during those 4 days units are 125% (5/4)
>> And Units always show the MAXIMUM, not the AVERAGE
>>
>> Hope this helps,
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Daniel" <daniel(a)discussions.microsoft.com.> wrote in message
>> news:E0787461-0F79-4777-84C9-3DF6D4E181AC(a)microsoft.com...
>> > Hello,
>> > Usually Units = Work / Duration, but in some case it seems this formula
>> > doesn't work.
>> > I performed some basic tests in project:
>> > First test: I created a fixed duration task:
>> > 1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
>> > Remaining work =5d
>> > I changed Rem Work from 5d to 6d, the task become
>> > Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is
>> > fine.
>> >
>> > Second test: I created a fixed duration task:
>> > 1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d
>> > and
>> > Remaining work=4d
>> > I changed Rem Work from 4d to 5d, the task become
>> > Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work
>> > =5d
>> > Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)
>> >
>>
>>
>> .
>>