From: Shahriar Nour Khondokar on 19 Oct 2009 22:34 I am preparing the schedule for a project where multiple resources are going to work. The project has a custom project calendar with a 7-hour working day. This calendar was prepared from here: Tools > Changing Working Time > Exceptions, Work Weeks > Details. Then tasks were created and resources were added. But one of the resources, Tom, will not be able to work 7hrs every day for the whole duration of the project. On certain days he can work 8hrs (this is happening on 2 days, 10/19 and 10/20) while on other days he can work 5hrs a day (on 10/26, 10/27). To account for this situation, I went to Resource Sheet view, double clicked Tom to bring up the Resource Information dialog box and from the General tab entered his Resource Availability as below: Available From: 10/12/09 … Available To: 10/18/09 … Units: 100% Available From: 10/19/09 … Available To: 10/18/20 … Units: 114% (8/7*100) Available From: 10/21/09 … Available To: 10/25/09 … Units: 100% Available From: 10/26/09 … Available To: 10/27/09 … Units: 71% (5/7*100) Available From: 10/28/09 … Available To: 10/18/10 … Units: 100% (One isolated question: is it necessary to enter the information as in row 1, 3 & 5? Or is there any easier alternative?) But problems arise when a task may last for several days. For example, if a task starts on 10/26 and lasts 4 days, the task is scheduled as if Tom is working 5hrs for the whole duration of the task although he can provide 5hrs on the first two days only, the remaining 2 days he can work 7hrs every day. So, my questions are: 1. How do I get around this error so that Tom is scheduled to work 5hrs only on 10/26 and 10/27 while he is scheduled 7hrs of work on 10/28 and 10/29 as is the default working hours for the project? 2. Is there a better more accurate/appropriate way to account for situations such as described above? Please provide some details.
From: Rob Schneider on 20 Oct 2009 00:44 Shahriar, See other thread, initiated 15/10/09 16:14 where lots of people replied to you. --rms www.rmschneider.com Shahriar Nour Khondokar wrote: > I am preparing the schedule for a project where multiple resources are going > to work. > The project has a custom project calendar with a 7-hour working day. This > calendar was prepared from here: > Tools > Changing Working Time > Exceptions, Work Weeks > Details. > Then tasks were created and resources were added. > But one of the resources, Tom, will not be able to work 7hrs every day for > the whole duration of the project. > On certain days he can work 8hrs (this is happening on 2 days, 10/19 and > 10/20) while on other days he can work 5hrs a day (on 10/26, 10/27). > To account for this situation, I went to Resource Sheet view, double clicked > Tom to bring up the Resource Information dialog box and from the General tab > entered his Resource Availability as below: > Available From: 10/12/09 … Available To: 10/18/09 … Units: 100% > Available From: 10/19/09 … Available To: 10/18/20 … Units: 114% (8/7*100) > Available From: 10/21/09 … Available To: 10/25/09 … Units: 100% > Available From: 10/26/09 … Available To: 10/27/09 … Units: 71% (5/7*100) > Available From: 10/28/09 … Available To: 10/18/10 … Units: 100% > (One isolated question: is it necessary to enter the information as in row > 1, 3 & 5? Or is there any easier alternative?) > But problems arise when a task may last for several days. For example, if a > task starts on 10/26 and lasts 4 days, the task is scheduled as if Tom is > working 5hrs for the whole duration of the task although he can provide 5hrs > on the first two days only, the remaining 2 days he can work 7hrs every day. > So, my questions are: > 1. How do I get around this error so that Tom is scheduled to work 5hrs only > on 10/26 and 10/27 while he is scheduled 7hrs of work on 10/28 and 10/29 as > is the default working hours for the project? > 2. Is there a better more accurate/appropriate way to account for situations > such as described above? Please provide some details.
From: JulieS on 20 Oct 2009 07:48 Hi Rob, Unfortunately due to some problems with the MS Servers, not all of the responses have made it back to the list in the web site. Julie "Rob Schneider" <rmschne(a)yahoo_but_not_often_checked.com> wrote in message news:eX%233MAUUKHA.3404(a)TK2MSFTNGP04.phx.gbl... > Shahriar, > > See other thread, initiated 15/10/09 16:14 where lots of people > replied to you. > > --rms > > www.rmschneider.com <snip>
From: JulieS on 20 Oct 2009 07:48 Shahriar Nour Khondokar -- it looks as though you are having trouble finding your other posts. See the following page from google groups for all 3 of your identical posts and the responses. http://groups.google.com/group/microsoft.public.project/browse_thread/thread/9141026c9e4f14a5/894d8738ba19e05c?lnk=gst&q=available+units+of+an+individual+resource#894d8738ba19e05c Read those responses and if you still have questions, please post your specific questions related to the answers you've been given. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "Shahriar Nour Khondokar" <ShahriarNourKhondokar(a)discussions.microsoft.com> wrote in message news:5B277CB3-5279-4995-997A-3D7DD380EC50(a)microsoft.com... >I am preparing the schedule for a project where multiple resources >are going > to work. > The project has a custom project calendar with a 7-hour working > day. This > calendar was prepared from here: > Tools > Changing Working Time > Exceptions, Work Weeks > Details. > Then tasks were created and resources were added. > But one of the resources, Tom, will not be able to work 7hrs every > day for > the whole duration of the project. > On certain days he can work 8hrs (this is happening on 2 days, > 10/19 and > 10/20) while on other days he can work 5hrs a day (on 10/26, > 10/27). > To account for this situation, I went to Resource Sheet view, > double clicked > Tom to bring up the Resource Information dialog box and from the > General tab > entered his Resource Availability as below: > Available From: 10/12/09 . Available To: 10/18/09 . Units: 100% > Available From: 10/19/09 . Available To: 10/18/20 . Units: 114% > (8/7*100) > Available From: 10/21/09 . Available To: 10/25/09 . Units: 100% > Available From: 10/26/09 . Available To: 10/27/09 . Units: 71% > (5/7*100) > Available From: 10/28/09 . Available To: 10/18/10 . Units: 100% > (One isolated question: is it necessary to enter the information > as in row > 1, 3 & 5? Or is there any easier alternative?) > But problems arise when a task may last for several days. For > example, if a > task starts on 10/26 and lasts 4 days, the task is scheduled as if > Tom is > working 5hrs for the whole duration of the task although he can > provide 5hrs > on the first two days only, the remaining 2 days he can work 7hrs > every day. > So, my questions are: > 1. How do I get around this error so that Tom is scheduled to work > 5hrs only > on 10/26 and 10/27 while he is scheduled 7hrs of work on 10/28 and > 10/29 as > is the default working hours for the project? > 2. Is there a better more accurate/appropriate way to account for > situations > such as described above? Please provide some details.
From: JulieS on 20 Oct 2009 09:14 Shahriar Nour Khondokar -- it looks as though you are having trouble finding your other posts. See the following page from google groups for all 3 of your identical posts and the responses. http://groups.google.com/group/microsoft.public.project/browse_thread/thread/9141026c9e4f14a5/894d8738ba19e05c?lnk=gst&q=available+units+of+an+individual+resource#894d8738ba19e05c Read those responses and if you still have questions, please post your specific questions related to the answers you've been given. I hope this helps. Let us know how you get along. Julie Project MVP "Shahriar Nour Khondokar" wrote: > I am preparing the schedule for a project where multiple resources are going > to work. > The project has a custom project calendar with a 7-hour working day. This > calendar was prepared from here: > Tools > Changing Working Time > Exceptions, Work Weeks > Details. > Then tasks were created and resources were added. > But one of the resources, Tom, will not be able to work 7hrs every day for > the whole duration of the project. > On certain days he can work 8hrs (this is happening on 2 days, 10/19 and > 10/20) while on other days he can work 5hrs a day (on 10/26, 10/27). > To account for this situation, I went to Resource Sheet view, double clicked > Tom to bring up the Resource Information dialog box and from the General tab > entered his Resource Availability as below: > Available From: 10/12/09 … Available To: 10/18/09 … Units: 100% > Available From: 10/19/09 … Available To: 10/18/20 … Units: 114% (8/7*100) > Available From: 10/21/09 … Available To: 10/25/09 … Units: 100% > Available From: 10/26/09 … Available To: 10/27/09 … Units: 71% (5/7*100) > Available From: 10/28/09 … Available To: 10/18/10 … Units: 100% > (One isolated question: is it necessary to enter the information as in row > 1, 3 & 5? Or is there any easier alternative?) > But problems arise when a task may last for several days. For example, if a > task starts on 10/26 and lasts 4 days, the task is scheduled as if Tom is > working 5hrs for the whole duration of the task although he can provide 5hrs > on the first two days only, the remaining 2 days he can work 7hrs every day. > So, my questions are: > 1. How do I get around this error so that Tom is scheduled to work 5hrs only > on 10/26 and 10/27 while he is scheduled 7hrs of work on 10/28 and 10/29 as > is the default working hours for the project? > 2. Is there a better more accurate/appropriate way to account for situations > such as described above? Please provide some details.
|
Pages: 1 Prev: MSP 07 pro visual reports Next: 92 KewaSa.com DDL Torrents |