From: Quizzed again on 6 May 2010 13:18 This seems messed up to me but please tell me if you also see this. In MSP2007 and also MSP2003, I have discovered that in projects without resources that if I save a baseline in a file, with no resources at all, that the SW is calculating what would equal 1 FTE worth of baseline work on each non-zero duration task. The baseline work in this case can be seen in a resource usage view if you add the baseline work field. The baseline work is not timephased. Why woud it be doing this and how do I stop it? I tested with MSP SP2 and Dec CU and also the April 2010 CU. I also tested on other files in MSP2003. Thanks! |