From: Thillai on 31 Mar 2010 08:46 What is the formula for a custom field to show the expected amount of time to be spent on a task on a particular day? Can anyone help me for this?
From: Dale Howard [MVP] on 31 Mar 2010 09:52 Thillai -- You need to examine the assignment Work field in either the Task Usage view or Resource Usage view. If you apply the Task Usage view and zoom the timescale to Weeks Over Days, you will see the assignment Work field in the right half of the view (the timephased grid). You can examine the Work assigned to a resource on any day. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Thillai" <Thillai(a)discussions.microsoft.com> wrote in message news:72F03C7C-1657-4B70-BBC3-3640ECCEDE14(a)microsoft.com... > What is the formula for a custom field to show the expected amount of time > to > be spent on a task on a particular day? > > Can anyone help me for this?
From: Andrew Lavinsky on 31 Mar 2010 10:00 Why do you need a formula? Just go to the Resource or Task Usage screens and zoom in on the chart until it's the right level of detail. Or is there something else you're looking for? - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > What is the formula for a custom field to show the expected amount of > time to be spent on a task on a particular day? > > Can anyone help me for this? >
From: Jan De Messemaeker on 31 Mar 2010 11:11
Hi, There is, as my learned colleagues pointed out, a simple way to read that value in a Usage view. However, if you really want what you ask for in a custom field, that cannot be done by a formula. You will need VBA coding. HTH -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Thillai" <Thillai(a)discussions.microsoft.com> wrote in message news:72F03C7C-1657-4B70-BBC3-3640ECCEDE14(a)microsoft.com... > What is the formula for a custom field to show the expected amount of time > to > be spent on a task on a particular day? > > Can anyone help me for this? |