From: scootr on 7 Apr 2010 12:46 There is a 700 feet rotating conveyor. Moving at a rate of 7.5 feet per minute. I know it takes 93 minutes to make one revolution. How long will it take to get 500 parts off the line? The parts are spaced 1 foot apart. I need a formula that can calculate this. Can somebody help me?
From: Gord Dibben on 7 Apr 2010 13:00 7.5 parts per minute. =500/7.5 returns 66.66667 minutes Gord Dibben MS Excel MVP On Wed, 7 Apr 2010 09:46:06 -0700, scootr <scootr(a)discussions.microsoft.com> wrote: >There is a 700 feet rotating conveyor. >Moving at a rate of 7.5 feet per minute. >I know it takes 93 minutes to make one revolution. > >How long will it take to get 500 parts off the line? >The parts are spaced 1 foot apart. > >I need a formula that can calculate this. Can somebody help me?
From: dlw on 7 Apr 2010 13:20 so, one part per foot, moving at 7.5 feet per minute, that means you are getting 7.5 parts per minute, divide 500 parts by 7.5 parts per minute gives you 66.6666666666666666 minutes to get 500 parts "scootr" wrote: > There is a 700 feet rotating conveyor. > Moving at a rate of 7.5 feet per minute. > I know it takes 93 minutes to make one revolution. > > How long will it take to get 500 parts off the line? > The parts are spaced 1 foot apart. > > I need a formula that can calculate this. Can somebody help me?
From: Bob I on 7 Apr 2010 13:30 Sounds like homework. scootr wrote: > There is a 700 feet rotating conveyor. > Moving at a rate of 7.5 feet per minute. > I know it takes 93 minutes to make one revolution. > > How long will it take to get 500 parts off the line? > The parts are spaced 1 foot apart. > > I need a formula that can calculate this. Can somebody help me?
From: trip_to_tokyo on 7 Apr 2010 13:54 EXCEL 2007 I have just put up a file for you at:- http://www.pierrefondes.com/ Item number 90 (at the time of posting). You can change any of the input cells (I 13, K 13, M 16 or J 22) and the result in minutes (cell M 26) will get calculated for you automatically. If my comments have helped please hit Yes. Thanks. "scootr" wrote: > There is a 700 feet rotating conveyor. > Moving at a rate of 7.5 feet per minute. > I know it takes 93 minutes to make one revolution. > > How long will it take to get 500 parts off the line? > The parts are spaced 1 foot apart. > > I need a formula that can calculate this. Can somebody help me?
|
Next
|
Last
Pages: 1 2 Prev: Return value greater than in LOOKUP Next: I need to show a % of a number |