From: The_Betty on 8 Apr 2010 23:13 I've been able to merge the schedules but I've been unable to send the consolidated file via email. What am I doing wrong?
From: Andrew Lavinsky on 8 Apr 2010 23:32
Remove the links and e-mail it. Doubleclick on the inserted projects, go to the Advanced Tab, and deselect the option to link to a file. That will embed the inserted project into the master. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > I've been able to merge the schedules but I've been unable to send the > consolidated file via email. What am I doing wrong? > |