From: Yannis on
Thanks Jan. I did follow the steps and managed to schedule the project. For
reference, I created a new 'Enterprise Calendar' and then assigned it to the
selected tasks.

"Jan De Messemaeker" wrote:

> Hi,
>
> Providing you have authority to defien new base calendars, do as follows:
> In the special project, define a working calendar 1 day per week
> Select all the tasks this resource is to work on
> Click Task Information, Advacnced tab
> Set the new base calendar as task calendar, check "Scheduling ignores
> resource calendars"
>
> If one of these tasks has more than one resoruce attached you may be in
> trouble, but if not, this is the (only) way
>
> HTH
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Yannis" <Yannis(a)discussions.microsoft.com> wrote in message
> news:DCC003E8-59E1-468E-9F5C-3F1221DA8A81(a)microsoft.com...
> > Hello,
> >
>
> > we need to set a resource to only work for one (1) day per week on a
> > specific project (because we want to book the rest 4 days to work in
> > another
> > project).
> >
> > [At the Enterprise Pool level, the resource is correctly setup to work
> > five
> > (5) days per week]
> >
> > Is there any way we can achieve this?
> >
> > Thanks in advance, YP
>
>
> .
>