From: RK on 5 Aug 2010 00:53 Hi, folks. I've been experimenting with a few project management applications and am now trying Openproj. All durations are set to working days as a default so going from, say Thursday to Monday, shows up as only 3 days duration instead of 5 day as with calendar-day durations. I hope nobody minds asking this here but I searched Openproj help and it's no help. How do I switch from working-day durations to calendar-day durations in Openproj? TIA. -- Bob |