From: Nifta on
I have four milestones dates defined for my project.

I'd like to have some way of displaying which milestone a task is completed
during.

My preferred way would be to change the colour of the Gantt bar (or the task
name) depending upon which Milestone it completes during.

I have no idea how to do this (I'm very new to Project)

Any help appreciated :)


From: Andrew Lavinsky on
Not sure I follow, but a variation of this (somewhat older blog post) might
be appropriate.

http://evildoctorporkchop.spaces.live.com/blog/cns!88E61D218103A246!1431.entry

"Nifta" wrote:

> I have four milestones dates defined for my project.
>
> I'd like to have some way of displaying which milestone a task is completed
> during.
>
> My preferred way would be to change the colour of the Gantt bar (or the task
> name) depending upon which Milestone it completes during.
>
> I have no idea how to do this (I'm very new to Project)
>
> Any help appreciated :)
>
>