From: Mike Einhorn on
Hello,

For a particular project I would like Project to use an alternate rate table
for a resource. Instead of editing the Cost Rate Table for each task can I
somehow set a default for the whole project?

Thanks,

Mike Einhorn
From: John on
In article <59C4A51A-0B3E-4F7F-80FB-540FDFD70766(a)microsoft.com>,
Mike Einhorn <MikeEinhorn(a)discussions.microsoft.com> wrote:

> Hello,
>
> For a particular project I would like Project to use an alternate rate table
> for a resource. Instead of editing the Cost Rate Table for each task can I
> somehow set a default for the whole project?
>
> Thanks,
>
> Mike Einhorn

Mike,
Since you imply the alternate rate is for a given resource why not
simply set that resource's rate appropriately?

Cost rate table information only applies to assignments which are
viewable on either the Resource or Task Usage views. Unfortunately there
is no default setting to do what I think you want. It could be done with
a VBA macro but other than that I think you're stuck with manual entry
for each assignment.

John
Project MVP
From: Jan De Messemaeker on

Hi,
In resource usage view, show the cost rate table column, set the appropriate
CRT for the first assignment of the reosurce, then drag this value down for
all the resource's assignments.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availabliy check:
http://users.online.be/prom-ade/Calendar.pdf
"Mike Einhorn" <MikeEinhorn(a)discussions.microsoft.com> wrote in message
news:59C4A51A-0B3E-4F7F-80FB-540FDFD70766(a)microsoft.com...
> Hello,
>
> For a particular project I would like Project to use an alternate rate
> table
> for a resource. Instead of editing the Cost Rate Table for each task can
> I
> somehow set a default for the whole project?
>
> Thanks,
>
> Mike Einhorn