Prev: prioritising resource
Next: Task Usage View to Excel
From: Rajiv Sharma Rajiv on 6 Apr 2010 07:01 Out of these two, which is used for calculating SPI ? "Jim Aksel" wrote: > %Complete is a duration based measure of complete. A 10 day task is 60% > complete on day 6. > > %Work Complete claims against the amount of work loaded into a task. If the > work is level loaded (same number of hours/day) then %Complete and %Work > Complete essentially accomplish the same thing. > > Here is a more complex example. Two workers are assigned to a 10 day task. > The work is loaded as 8 hours/day for the first week and 1 hour/day for the > second week. Total work is 45 hours. for convenience Worker1 works the first > week, Worker2 works the second week. On day 6 the task is 60% Complete for > duration, but is 41/45 (91%) Work Complete, assuming only one worker per day > on the task. > > Try this, do some research on Physical%Complete as well. It relates a > little more to the value produced. For our example above, suppose we assign > two workers to the task. The first week Worker1 works at $30/hour for 40 > hours. The following week Worker2 is a consultant at $125/hr and he works > the second week (alone). The total value of the task is 10 days, 45 hours, > $1825 (40*30+5*125). On day 6, assuming everyone accomplished what they are > supposed to: Physical%Complete goes to ($1200+$125)/$1825 = 73% . To use > this technique you need costed resources and a baseline. I know this was > beyond your question, so post back if you need additional guidance. > -- > If this post was helpful, please consider rating it. > > Jim Aksel, MVP > > Check out my blog for more information: > http://www.msprojectblog.com > > > > "neostar77" wrote: > > > What is the difference between using % complete and % work complete columns? > > > > What are the major impacts and limitations of using each?
From: G�rard Ducouret on 6 Apr 2010 15:03 Rajiv, None, The SPI is calculated according to the formula : SPI = BCWP / BCWS G�rrad Ducouret "Rajiv Sharma" <Rajiv Sharma(a)discussions.microsoft.com> a �crit dans le message de news: 9B3DE00B-3137-49D6-82AB-4B29CC65D1B6(a)microsoft.com... > Out of these two, which is used for calculating SPI ? > > "Jim Aksel" wrote: > >> %Complete is a duration based measure of complete. A 10 day task is 60% >> complete on day 6. >> >> %Work Complete claims against the amount of work loaded into a task. If >> the >> work is level loaded (same number of hours/day) then %Complete and %Work >> Complete essentially accomplish the same thing. >> >> Here is a more complex example. Two workers are assigned to a 10 day >> task. >> The work is loaded as 8 hours/day for the first week and 1 hour/day for >> the >> second week. Total work is 45 hours. for convenience Worker1 works the >> first >> week, Worker2 works the second week. On day 6 the task is 60% Complete >> for >> duration, but is 41/45 (91%) Work Complete, assuming only one worker per >> day >> on the task. >> >> Try this, do some research on Physical%Complete as well. It relates a >> little more to the value produced. For our example above, suppose we >> assign >> two workers to the task. The first week Worker1 works at $30/hour for 40 >> hours. The following week Worker2 is a consultant at $125/hr and he >> works >> the second week (alone). The total value of the task is 10 days, 45 >> hours, >> $1825 (40*30+5*125). On day 6, assuming everyone accomplished what they >> are >> supposed to: Physical%Complete goes to ($1200+$125)/$1825 = 73% . To >> use >> this technique you need costed resources and a baseline. I know this was >> beyond your question, so post back if you need additional guidance. >> -- >> If this post was helpful, please consider rating it. >> >> Jim Aksel, MVP >> >> Check out my blog for more information: >> http://www.msprojectblog.com >> >> >> >> "neostar77" wrote: >> >> > What is the difference between using % complete and % work complete >> > columns? >> > >> > What are the major impacts and limitations of using each?
|
Pages: 1 Prev: prioritising resource Next: Task Usage View to Excel |