From: Erin on 11 May 2010 17:09 I wrote a simple equation Additional Costs = ([Cost]) * 0.08 It was accepted into the equation but in the column it show "#ERROR" Does anyone have any suggestions or know what I did wrong?
From: Jack Dahlgren MVP on 11 May 2010 18:03 Hit the F9 key to recalculate. What type of field is the Additional Costs field? -Jack Dahlgren "Erin" <Erin(a)discussions.microsoft.com> wrote in message news:EE0A8BFF-7179-4168-80EC-DE1881F8E284(a)microsoft.com... > I wrote a simple equation > > Additional Costs = ([Cost]) * 0.08 > > It was accepted into the equation but in the column it show "#ERROR" > > Does anyone have any suggestions or know what I did wrong?
|