From: Hadi on 27 May 2010 17:25 Experts, I have been importing excel data to Project for years and never seen this problem. Today I was helping one of our users to import a list of assignments from Excel to a project schedule. We opened the excel file and went through the import wizard until we got to Finish. it went through but no data came in. I tried the same excel and same project files on my computer and everything worked fine. I did see that he did not have the "allow files with legacy format to open", but when I checked it didnt help either. what ami missing Hadi
From: JulieS on 27 May 2010 19:50 Hadi, What did you set as the merge key? Can you give us more details about the merge fields you are using? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/27/2010 5:25 PM, Hadi wrote: > Experts, > > I have been importing excel data to Project for years and never seen this > problem. Today I was helping one of our users to import a list of assignments > from Excel to a project schedule. We opened the excel file and went through > the import wizard until we got to Finish. it went through but no data came > in. I tried the same excel and same project files on my computer and > everything worked fine. I did see that he did not have the "allow files with > legacy format to open", but when I checked it didnt help either. what ami > missing > > Hadi
From: Andrew Lavinsky on 27 May 2010 20:13 What're you using for the Primary Key? Is it possible that got changed on the user machine? "Hadi" wrote: > Experts, > > I have been importing excel data to Project for years and never seen this > problem. Today I was helping one of our users to import a list of assignments > from Excel to a project schedule. We opened the excel file and went through > the import wizard until we got to Finish. it went through but no data came > in. I tried the same excel and same project files on my computer and > everything worked fine. I did see that he did not have the "allow files with > legacy format to open", but when I checked it didnt help either. what ami > missing > > Hadi
From: Hadi on 28 May 2010 13:49 This was an Append taks or Merge so I did not use a merge key, plus i took the same project schedule and excel sheet, tried it on my machine and work perfectly "JulieS" wrote: > Hadi, > > What did you set as the merge key? Can you give us more details > about the merge fields you are using? > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > > On 5/27/2010 5:25 PM, Hadi wrote: > > Experts, > > > > I have been importing excel data to Project for years and never seen this > > problem. Today I was helping one of our users to import a list of assignments > > from Excel to a project schedule. We opened the excel file and went through > > the import wizard until we got to Finish. it went through but no data came > > in. I tried the same excel and same project files on my computer and > > everything worked fine. I did see that he did not have the "allow files with > > legacy format to open", but when I checked it didnt help either. what ami > > missing > > > > Hadi > . >
From: JulieS on 29 May 2010 09:20 If it works fine on your computer and does not function on another, I've got to guess it is not specific to Project. Things to check: Same version of Excel? Same SP to Excel and Project? Same OS? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/28/2010 1:49 PM, Hadi wrote: > This was an Append taks or Merge so I did not use a merge key, plus i took > the same project schedule and excel sheet, tried it on my machine and work > perfectly > > "JulieS" wrote: > >> Hadi, >> >> What did you set as the merge key? Can you give us more details >> about the merge fields you are using? >> >> I hope this helps. Let us know how you get along. >> >> Julie >> Project MVP >> >> Visit http://project.mvps.org/ for the FAQs and additional >> information about Microsoft Project >> >> On 5/27/2010 5:25 PM, Hadi wrote: >>> Experts, >>> >>> I have been importing excel data to Project for years and never seen this >>> problem. Today I was helping one of our users to import a list of assignments >>> from Excel to a project schedule. We opened the excel file and went through >>> the import wizard until we got to Finish. it went through but no data came >>> in. I tried the same excel and same project files on my computer and >>> everything worked fine. I did see that he did not have the "allow files with >>> legacy format to open", but when I checked it didnt help either. what ami >>> missing >>> >>> Hadi >> . >>
|