From: Amey on 16 Feb 2010 08:04 dear sir, I am using project 2007.I want to link two different sheets.I want to make activities of one sheet to be predecessor of another. so when I do to tools,links between projects, it doesnt show any active option.How can I do it. -- Amey B. Vidvans, Planning Engineer Vidvans_amey(a)rediffmail.com
From: AmiProject on 16 Feb 2010 08:22 Amey, You need to insert one sheet to another first (menu Insert/Project). -- Denis http://www.amiproject.com Microsoft Project online viewer "Amey" wrote: > dear sir, > I am using project 2007.I want to link two different sheets.I want to make > activities of one sheet to be predecessor of another. so when I do to > tools,links between projects, it doesnt show any active option.How can I do > it. > -- > Amey B. Vidvans, > Planning Engineer > Vidvans_amey(a)rediffmail.com
From: Dale Howard [MVP] on 16 Feb 2010 08:46 Amey -- Do the following: 1. Open both of the project files. 2. Click Window - New Window. 3. In the New Window dialog, select both of the projects and then click the OK button. Microsoft Project creates a temporary master project, consisting of your two projects as subprojects. 4. Expand the tasks in each of the subprojects. 5. Link tasks across projects as needed. 6. Click File - Close to close the temporary master project. 7. When prompted, click the No button to close the master project WITHOUT saving it. 8. When prompted again, click the Yes to All button to save the changes to each of the subprojects. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Amey" <Amey(a)discussions.microsoft.com> wrote in message news:DA78A317-92AF-4E22-AFA4-19FE53A11213(a)microsoft.com... > dear sir, > I am using project 2007.I want to link two different sheets.I want to make > activities of one sheet to be predecessor of another. so when I do to > tools,links between projects, it doesnt show any active option.How can I > do > it. > -- > Amey B. Vidvans, > Planning Engineer > Vidvans_amey(a)rediffmail.com
|
Pages: 1 Prev: Project Queue Next: Changing Start Date affects Duration and/or Work in 2007 (not in 2003) |