From: Terri on 9 Feb 2010 08:51 Thank You Everyone for the help "Steve House" wrote: > Additional notes ... > > When the task is Fixed Work and you edit Work hours, it behaves as if it was > Fixed Units and duration changes. > When the Task is Fixed Duration and you edit Duration hours, it behaves as > if it was Fixed Units and work changes. > When the task is Fixed Units and you edit Units, it behaves as if it was > Fixed Work and duration changes. > > -- > Steve House > MS Project Trainer & Consultant > > > "Terri" <Terri(a)discussions.microsoft.com> wrote in message > news:5335A162-CE30-4443-A443-1B0D2798BB08(a)microsoft.com... > > Using MSP 2007 > > > > I was added to a project that is in the proposal stage and took over an > > existing schedule. > > > > The original scheduler had it as fixed units, and did a preliminary > > resource > > loading. Now the estimates have changed and I need to adjust the hours. > > I > > want it to be fixed work and let the duration calculate based on amount of > > work. I did change all the task types to fixed work and then started > > adjusting the hours. > > > > My question, (I may not even have to worry about it, but it is bugging me) > > is when I adjust the hours on a resource using the gant chart view, split > > window, task details form on bottom split, the units are adjusting for > > some > > resources, but for some it is staying at whatever the unit percentage was > > there prior to the adjustment or is changing to 100% for less that 100% > > effot. > > > > Example: > > > > Total work for the activity is 120 hours split over 3 resources 100 hours > > for 1 and 10 hours each for the other 2. > > > > The 100 hours is giving me 12.5 day duration, since this is engineering, I > > am allowing some float so I adjust the duration to 15 days. This reduced > > the > > units for the 100 hours correctly to 83% the other two are staying at 100% > > which I would have expected to see 8% on. Is there an explanation why > > some > > units adjust correctly while other stay where they were prior to the > > adjustments? > > > > Thanks in advance for any help. > > > > > > > > . >
First
|
Prev
|
Pages: 1 2 Prev: Project Tasks not displayed under My Tasks in PWA Next: Deleting a calender? |