From: Amy U on 25 May 2010 11:15 Why are actual hours automatically appearing on a resources timesheet? They go to open their timesheet and there are hours there that they did not log.
From: Barbara Henhapl on 27 May 2010 05:59 Hi Amy, does the project manager of these tasks update project progress manually? If he does (e.g. set %complete in his project plan), 'Work' for each day will be copied to 'Actual Work' for a period. These hours will be pre-populated in timesheets. If my assumption is correct, tell them to change remaining work rather than %complete to update their project progress. Regards Barbara P.s.: This forum will be closed in the near future. For new questions regarding Project Server you should have a look at http://social.technet.microsoft.com/Forums/en-US/projectserver2010general (don't get confused by "2010" in the name) "Amy U" <AmyU(a)discussions.microsoft.com> schrieb im Newsbeitrag news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171(a)microsoft.com... > Why are actual hours automatically appearing on a resources timesheet? > They > go to open their timesheet and there are hours there that they did not > log.
From: Amy U on 3 Jun 2010 13:55 Barbara, I checked with the PM and here was her response, "I do not manage my plans that way. The only time that I modify % complete is if I remove all work and the % does not change. Below is an example of when I might modify the % complete, but again only if work is zero. Example: Task never started and determined it was not needed. Remove remaining work using task usage view. Modify % complete in either the task detail or column inserted in view." Your thoughts? "Barbara Henhapl" wrote: > Hi Amy, > > does the project manager of these tasks update project progress manually? If > he does (e.g. set %complete in his project plan), 'Work' for each day will > be copied to 'Actual Work' for a period. These hours will be pre-populated > in timesheets. If my assumption is correct, tell them to change remaining > work rather than %complete to update their project progress. > > Regards > Barbara > > P.s.: This forum will be closed in the near future. For new questions > regarding Project Server you should have a look at > http://social.technet.microsoft.com/Forums/en-US/projectserver2010general > (don't get confused by "2010" in the name) > > "Amy U" <AmyU(a)discussions.microsoft.com> schrieb im Newsbeitrag > news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171(a)microsoft.com... > > Why are actual hours automatically appearing on a resources timesheet? > > They > > go to open their timesheet and there are hours there that they did not > > log. >
|
Pages: 1 Prev: Changing Holiday in Enterprise Global Next: how to undo animation when "no animation |