From: DianneZ on
HI - Love this group - you are such a fund of information.

in project 2007 -
I cannot explain why assigning overtime behaves differently if the task is
set to 100% complete first and then assign overtime or assign overtime and
then set 100% complete
EG:
task A - 24h - one resource
assign OT of 8h - Duration moves to 2days
add 8 hours to the work column to reflect that this is additional to the
24hours of work duration moves back to 3days work shows 10.67 hrs per day (OK
- understood)
mark complete - duration the same 3 days
Now.....
same duration task
task B - 24 h -one resource
MARK COMPLETE
then add 8 hrs OT
no change in duration! stays at 3D

It seems the orders matters - can you help me understand why the order of
setting complete matters?
Thanks wizards all!
From: Rod Gill on
In this scenario, I think because you have 100% complete, there is an actual
finish date. Actual dates never get re-calculated.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




"DianneZ" <DianneZ(a)discussions.microsoft.com> wrote in message
news:7AD6F75E-7CD1-462A-B1D1-CC0D527EB35A(a)microsoft.com...
> HI - Love this group - you are such a fund of information.
>
> in project 2007 -
> I cannot explain why assigning overtime behaves differently if the task is
> set to 100% complete first and then assign overtime or assign overtime
> and
> then set 100% complete
> EG:
> task A - 24h - one resource
> assign OT of 8h - Duration moves to 2days
> add 8 hours to the work column to reflect that this is additional to the
> 24hours of work duration moves back to 3days work shows 10.67 hrs per day
> (OK
> - understood)
> mark complete - duration the same 3 days
> Now.....
> same duration task
> task B - 24 h -one resource
> MARK COMPLETE
> then add 8 hrs OT
> no change in duration! stays at 3D
>
> It seems the orders matters - can you help me understand why the order of
> setting complete matters?
> Thanks wizards all!
>
> __________ Information from ESET Smart Security, version of virus
> signature database 5008 (20100407) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>

__________ Information from ESET Smart Security, version of virus signature database 5008 (20100407) __________

The message was checked by ESET Smart Security.

http://www.eset.com