From: Princess Bride Princess on
I have a section of my project that the hours just do nt roll correctly -
what is wrong?
Compensation 2,632.6 hrs
Determine High-level compensation strategy and plan to communicate 40 hrs
Establish Common Review Date 8 hrs
Determine Compensation Transition Plan 100 hrs
Complementation review and transition completed 20 hrs
Retention Bonus Plans 10 hrs
Determine if we owe any commission on sales that complete/turnover to us
after close 10 hrs
Implement Compensation Transition Plan 400 hrs
Begin Job Evaluation Process 10 hrs
Determine when to introduce StARS process 4 hrs

From: JulieS on
Hello Princess Bride (I love that book),

Ensure you do not have resource assigned to any summary level
tasks in addition to Mike's sage advice.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 2/26/2010 5:19 PM, Princess Bride wrote:
> I have a section of my project that the hours just do nt roll correctly -
> what is wrong?
> Compensation 2,632.6 hrs
> Determine High-level compensation strategy and plan to communicate 40 hrs
> Establish Common Review Date 8 hrs
> Determine Compensation Transition Plan 100 hrs
> Complementation review and transition completed 20 hrs
> Retention Bonus Plans 10 hrs
> Determine if we owe any commission on sales that complete/turnover to us
> after close 10 hrs
> Implement Compensation Transition Plan 400 hrs
> Begin Job Evaluation Process 10 hrs
> Determine when to introduce StARS process 4 hrs
>