From: Princess Bride Princess on 26 Feb 2010 17:19 I have a section of my project that the hours just do nt roll correctly - what is wrong? Compensation 2,632.6 hrs Determine High-level compensation strategy and plan to communicate 40 hrs Establish Common Review Date 8 hrs Determine Compensation Transition Plan 100 hrs Complementation review and transition completed 20 hrs Retention Bonus Plans 10 hrs Determine if we owe any commission on sales that complete/turnover to us after close 10 hrs Implement Compensation Transition Plan 400 hrs Begin Job Evaluation Process 10 hrs Determine when to introduce StARS process 4 hrs
From: JulieS on 26 Feb 2010 18:54 Hello Princess Bride (I love that book), Ensure you do not have resource assigned to any summary level tasks in addition to Mike's sage advice. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 2/26/2010 5:19 PM, Princess Bride wrote: > I have a section of my project that the hours just do nt roll correctly - > what is wrong? > Compensation 2,632.6 hrs > Determine High-level compensation strategy and plan to communicate 40 hrs > Establish Common Review Date 8 hrs > Determine Compensation Transition Plan 100 hrs > Complementation review and transition completed 20 hrs > Retention Bonus Plans 10 hrs > Determine if we owe any commission on sales that complete/turnover to us > after close 10 hrs > Implement Compensation Transition Plan 400 hrs > Begin Job Evaluation Process 10 hrs > Determine when to introduce StARS process 4 hrs >
|
Pages: 1 Prev: Page Breaks in Microsoft 2007 Next: Mary Lou Group By |