From: Jaylene on 4 Feb 2010 13:06 Let's say I have a 40 hour task for a single resource that is supposed to start on February 8. The resource is allocated 8 hours per day. As expected, Project schedules the task to be completed 5 days later on February 12. Let's say it's end of day Wednesday, February 10. My resource has made only 8 hours of progress since Monday. My remaining work is 32 hours, yet my finish date still reflects February 12. How do i get my finish date to reflect that there are 32 hours that remain from Wednesday? Reality says that my resource will not finish 32 hours of work until the following Tuesday, February 16.
From: Jan De Messemaeker on 4 Feb 2010 13:39 Hi, Enter 8 hrs of Actual Work. Then Tools, Tracking, Update Project Select the radio button "reschedule ..." and put Wednesday's date in the appropriate box. OK, and that's it. -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Jaylene" <Jaylene(a)discussions.microsoft.com> wrote in message news:4EDFF9DD-D338-4186-A797-3E90CE192644(a)microsoft.com... > Let's say I have a 40 hour task for a single resource that is supposed to > start on February 8. The resource is allocated 8 hours per day. As > expected, > Project schedules the task to be completed 5 days later on February 12. > > Let's say it's end of day Wednesday, February 10. My resource has made > only > 8 hours of progress since Monday. My remaining work is 32 hours, yet my > finish date still reflects February 12. How do i get my finish date to > reflect that there are 32 hours that remain from Wednesday? Reality says > that > my resource will not finish 32 hours of work until the following Tuesday, > February 16.
From: Sai on 4 Feb 2010 23:05 On Feb 4, 11:06 pm, Jaylene <Jayl...(a)discussions.microsoft.com> wrote: > Let's say I have a 40 hour task for a single resource that is supposed to > start on February 8. The resource is allocated 8 hours per day. As expected, > Project schedules the task to be completed 5 days later on February 12. > > Let's say it's end of day Wednesday, February 10. My resource has made only > 8 hours of progress since Monday. My remaining work is 32 hours, yet my > finish date still reflects February 12. How do i get my finish date to > reflect that there are 32 hours that remain from Wednesday? Reality says that > my resource will not finish 32 hours of work until the following Tuesday, > February 16. Besides Jan's answer, I suggest you the following setting to change the behaviour of how Project reschedules the completed and incomplet work of the task 1. After the Status date is set in Project Information dialog box 2. Choose Tools | Options, Calculation tab and under Schedule adjustments for early and late tasks section 3. You can turn on / off the below check boxes a Move end of completed parts after status date back to status date b Move end of completed parts after status date back to status date and And move start of remaining parts back to status date c Move start of remaining parts before status date forward to status date d Move start of remaining parts before status date forward to status date And move end of completed parts forward to status date Please let us if clears your question. - Sai, PMP, PMI-SP, MCT, MCTS http://saipower.wordpress.com
|
Pages: 1 Prev: Predecessors Next: Save Custom Table/Report? |