From: Sadad on 13 Apr 2010 12:13 PERFECT... IT WORKS :) Thanks you... "Biff" wrote: > Hi! > > Try this: > > A1 = start date > A2 = end date > > =NETWORKDAYS(A1+1,A2+1) > > If you need to exclude holidays: > > H1:H10 = list of holiday dates > > Entered as an array using the key combination of CTRL,SHIFT,ENTER. > > =NETWORKDAYS(A1+1,A2+1,H1:H10+1) > > Biff > > "Shay.C." <Shay.C.(a)discussions.microsoft.com> wrote in message > news:8A9FBEA5-9E73-485A-9CB8-10D7D567C293(a)microsoft.com... > > The NETWORKDAYS function regards Saturday and Sunday as weekends. I need > > to > > set Excel to regard Friday and Saturday as the weekend. > > >
|