From: Lee on
Good Morning!

How do you change a WBS number and its' sub numbers?

What I have is:
1
1.1
1.1.1
1.1.2

What I want is:
2
2.1
2.1.1
2.1.2

Thanks.

Lee

From: Andrew Lavinsky on
Project > Define WBS Code.

Set the first layer to Character, and manually type the "2" in the field.
You'll need to manually modify the code for each of the subsequent Tier
I activities.

For more information, feel free to check out this blog post on WBS modifications:
http://blogs.catapultsystems.com/epm/archive/2010/03/03/using-intelligent-wbs-codes-in-microsoft-project.aspx


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm