From: scottsoo9 on 17 Nov 2009 08:57 I have a spreadsheet from excel with numbers such as start and end date, % complete, % funds expended, hours expended, dollars authenticated, and dollars expended, travel costs, subcontractor costs, and amount invoiced and amount paid but with no actual resources. I need to put this into project. My problem besides being relatively new to project is that I do not know how to put that data in without supplying the actual resources in the resource sheet. (which i do not have) I can do things such as start and end date, and percent complete but after that it gets much more challenging for me. Any guidance on how I would go about doing this would be greatly appreciated. Thanks, Scott -- scottsoo9 ------------------------------------------------------------------------ scottsoo9's Profile: http://forums.techarena.in/members/155605.htm View this thread: http://forums.techarena.in/microsoft-project/1272109.htm http://forums.techarena.in
From: scottsoo9 on 17 Nov 2009 10:54 I forgot to mention that I am entering tasks that have already been completed. All my numbers are exact numbers and can not be changed. Not really sure what to do? -- scottsoo9 ------------------------------------------------------------------------ scottsoo9's Profile: http://forums.techarena.in/members/155605.htm View this thread: http://forums.techarena.in/microsoft-project/1272109.htm http://forums.techarena.in
From: "Steve House" sjhouse at hotmail dot on 19 Nov 2009 07:35
If the tasks have already been completed, what's the point of entering them into Project??? The software is designed to schedule FUTURE work, not report PAST work. While it certainly does do reporting, don't get me wrong, it is reporting the schedule as updated with actuals. The end result is similar to what you've already got in your Excel worksheets. Since you've already got the numbers that you would generate reports in Project to discover, why bother running them through Project? -- Steve House MS Project Trainer & Consultant "scottsoo9" <scottsoo9.41szrc(a)DoNotSpam.com> wrote in message news:scottsoo9.41szrc(a)DoNotSpam.com... > > I forgot to mention that I am entering tasks that have already been > completed. All my numbers are exact numbers and can not be changed. Not > really sure what to do? > > > -- > scottsoo9 > ------------------------------------------------------------------------ > scottsoo9's Profile: http://forums.techarena.in/members/155605.htm > View this thread: http://forums.techarena.in/microsoft-project/1272109.htm > > http://forums.techarena.in > |