From: ttorneby on 2 Jun 2010 15:32 I'm having huge problems finishing a plan I'm working on. Maybe someone here has some clever ideas. To take it from the beginning: This is a part of some school work, and I have a number of tasks, and for each of the tasks I have details on what the budget is, and the planned duration. At a specific point in time I have details on the completion rate of each task, as well as the money spent, and the actual duration. From these figures, I want MS Project to calculate figures such as BCWS, ACWP, BCWP, EAC, SPI and CPI. My problem is that I have not found a place to enter the budget cost for each task, without having to assign resources and all this. I've only found two coloums containing the word "budget", but neither of them allows me to enter values. Is there not a simple way to do this? Also, it seems like "actual duration" and "% work completed follow each other. F.ex. on a specific task, 13 out of 16 weeks are spent, but the work is only 75% completed. MS Project doesn't seem to accept this. I've attached a screeshot of what I'm working on, in case it might be at help. Any help on this matter is highly appreciated! +-------------------------------------------------------------------+ |Filename: screenshot.png | |Download: http://forums.techarena.in/attachment.php?attachmentid=11002| +-------------------------------------------------------------------+ -- ttorneby ------------------------------------------------------------------------ ttorneby's Profile: http://forums.techarena.in/members/227766.htm View this thread: http://forums.techarena.in/microsoft-project/1343078.htm http://forums.techarena.in
From: Trevor Rabey on 2 Jun 2010 23:53 It seems that you have been inserting all of these fields into the Entry Table, and it is fairly un-readable. Where's the bars? It is better to leave the Entry Table as it is defined with the original columns, and switch from the Entry Table to whatever table is of interest (Cost, Work, EV etc). To have costs you must either assign resources which have costs to tasks, or, alternatively, you must assign a Fixed Cost (see the Cost Table). Have you set a status date? Have you saved a baseline? Have you seen the Tracking Gantt View? Have you seen the Tracking Table? Are you familar with the Tracking Toolbar? Have you updated the progress properly, starting with the Actual Start, Actual Duration, Actual Finish? Have you been entering % Complete or % Work Complete (wrong). Hope this helps. -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "ttorneby" <ttorneby.4bym9c(a)DoNotSpam.com> wrote in message news:ttorneby.4bym9c(a)DoNotSpam.com... > > > I'm having huge problems finishing a plan I'm working on. Maybe someone > here has some clever ideas. > > To take it from the beginning: This is a part of some school work, and I > have a number of tasks, and for each of the tasks I have details on what > the budget is, and the planned duration. At a specific point in time I > have details on the completion rate of each task, as well as the money > spent, and the actual duration. From these figures, I want MS Project to > calculate figures such as BCWS, ACWP, BCWP, EAC, SPI and CPI. > > My problem is that I have not found a place to enter the budget cost for > each task, without having to assign resources and all this. I've only > found two coloums containing the word "budget", but neither of them > allows me to enter values. Is there not a simple way to do this? > > Also, it seems like "actual duration" and "% work completed follow each > other. F.ex. on a specific task, 13 out of 16 weeks are spent, but the > work is only 75% completed. MS Project doesn't seem to accept this. > > I've attached a screeshot of what I'm working on, in case it might be at > help. > > Any help on this matter is highly appreciated! > > > +-------------------------------------------------------------------+ > |Filename: screenshot.png | > |Download: http://forums.techarena.in/attachment.php?attachmentid=11002| > +-------------------------------------------------------------------+ > > -- > ttorneby > ------------------------------------------------------------------------ > ttorneby's Profile: http://forums.techarena.in/members/227766.htm > View this thread: http://forums.techarena.in/microsoft-project/1343078.htm > > http://forums.techarena.in >
From: "Steve House" sjhouse at hotmail dot on 6 Jun 2010 13:45 The "budget" Project refers to when calculating EV is the timephased baseline cost data. You are also confusing "% Complete" with "% Work Complete" - they are in fact two entirely different and separate metrics. "% Complete" refers strictly to duration, the passage of time, and carries no information about how much work has been done nor how much deliverable has been completed. It is impossible that at the end of 13 weeks into a 16 week duration task for the "% Complete" be 75%. Assuming that no scheduled work time has been missed, at the end of Week 13 into a 16 week task, the % complete is 13/16 or 81.25% by definition; it can be nothing else. If by "75% Complete" you mean as much deliverable has not been achieved by the end of Week 13 as you had expected, you need to revise the estimated total duration upward from the original 16 weeks. If you are 75% complete after working for 13 weeks, the total duration needs to be 17.33 weeks. The "% Work Complete" MIGHT be 81.25%, if the work contour is flat, but it could also be some wildly different number from that if it is contoured. -- Steve House MS Project Trainer & Consultant "ttorneby" <ttorneby.4bym9c(a)DoNotSpam.com> wrote in message news:ttorneby.4bym9c(a)DoNotSpam.com... > > I'm having huge problems finishing a plan I'm working on. Maybe someone > here has some clever ideas. > > To take it from the beginning: This is a part of some school work, and I > have a number of tasks, and for each of the tasks I have details on what > the budget is, and the planned duration. At a specific point in time I > have details on the completion rate of each task, as well as the money > spent, and the actual duration. From these figures, I want MS Project to > calculate figures such as BCWS, ACWP, BCWP, EAC, SPI and CPI. > > My problem is that I have not found a place to enter the budget cost for > each task, without having to assign resources and all this. I've only > found two coloums containing the word "budget", but neither of them > allows me to enter values. Is there not a simple way to do this? > > Also, it seems like "actual duration" and "% work completed follow each > other. F.ex. on a specific task, 13 out of 16 weeks are spent, but the > work is only 75% completed. MS Project doesn't seem to accept this. > > I've attached a screeshot of what I'm working on, in case it might be at > help. > > Any help on this matter is highly appreciated! > > > +-------------------------------------------------------------------+ > |Filename: screenshot.png | > |Download: http://forums.techarena.in/attachment.php?attachmentid=11002| > +-------------------------------------------------------------------+ > > -- > ttorneby > ------------------------------------------------------------------------ > ttorneby's Profile: http://forums.techarena.in/members/227766.htm > View this thread: http://forums.techarena.in/microsoft-project/1343078.htm > > http://forums.techarena.in >
|
Pages: 1 Prev: Project crashing during startup, how do I remedy? Next: project 2007 question |