From: Xiao on
Hello,

Project Professional 2007 + SP2
I have some tasks with Fixed Cost. But for some of them we got some more
cost.
In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
$1000 for a specific week. The cost of the task for that week jumps to
$2200.
How to enter discrepancies of Actual Cost on Fixed Cost tasks?
Thanks



From: Rod Gill on
When entering actual cost, do so in the spreadsheet side of the view, or
make sure you delete the original $1,000 if it happened in a different week.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




"Xiao" <nospam(a)nospam.com> wrote in message
news:e7ukIpc8KHA.420(a)TK2MSFTNGP02.phx.gbl...
> Hello,
>
> Project Professional 2007 + SP2
> I have some tasks with Fixed Cost. But for some of them we got some more
> cost.
> In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
> $1000 for a specific week. The cost of the task for that week jumps to
> $2200.
> How to enter discrepancies of Actual Cost on Fixed Cost tasks?
> Thanks
>
>
>
> __________ Information from ESET Smart Security, version of virus
> signature database 5110 (20100512) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>

__________ Information from ESET Smart Security, version of virus signature database 5110 (20100512) __________

The message was checked by ESET Smart Security.

http://www.eset.com