Prev: As-built Calendars
Next: Print to PDF file
From: kamran on 6 Apr 2010 15:02 Hi When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the project calculates 3 days, I like it to calculate 5 day, which means including the start and end date in duration. How can I set this up. Please help.... Thank you
From: Andrew Lavinsky on 6 Apr 2010 15:15 Typically, the system DOES include the Start and End date in the system. In your example 4/1 - 4/5, that is three days: Thursday, Friday and Monday. Do you wish to override the weekends? If so, simply create a new 7 day calendar in Tools > Change Working Time and apply to the project and/or resources. Then make sure the settings in Tools > Options > Calendar map to your new settings. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > Hi When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the > project calculates 3 days, I like it to calculate 5 day, which means > including the start and end date in duration. How can I set this up. > Please help.... > > Thank you >
From: kamran on 6 Apr 2010 16:49 Thank you for the information. I still have a problem setting the newly created 7-working day calender as a default for my project. My tasks do not recognize this new setting. My task timeline keeps going back to the standard calender. Thank you "Andrew Lavinsky" wrote: > Typically, the system DOES include the Start and End date in the system. > In your example 4/1 - 4/5, that is three days: Thursday, Friday and Monday. > Do you wish to override the weekends? If so, simply create a new 7 day > calendar in Tools > Change Working Time and apply to the project and/or resources. > > Then make sure the settings in Tools > Options > Calendar map to your new > settings. > > - Andrew Lavinsky > Blog: http://blogs.catapultsystems.com/epm > > > Hi When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the > > project calculates 3 days, I like it to calculate 5 day, which means > > including the start and end date in duration. How can I set this up. > > Please help.... > > > > Thank you > > > > > . >
From: "Steve House" sjhouse at hotmail dot on 6 Apr 2010 17:43 Once you have created the calendar, go to the Project menu, Project Information, and designate it as the Project Calendar. The Timeline display, though will still show the non-working days from the Standard calendar untill you also right-click in the timeline, chose "timescale," the non-working time tab, and switch from the Standard calendar to your new 7-day calendar. Remember though, a 7-day calendar implies that when work starts on a task, it proceeds every day without interruption. Don't your resources get a day off? When you assign Joe to work on a task with a 2 week duration, does the poor fellow really have to work every day until the task is done? -- Steve House MS Project Trainer & Consultant "kamran" <kamran(a)discussions.microsoft.com> wrote in message news:8CDE3EF2-E955-4DC8-9964-80A36B85BAEB(a)microsoft.com... > Thank you for the information. I still have a problem setting the newly > created 7-working day calender as a default for my project. My tasks do > not > recognize this new setting. My task timeline keeps going back to the > standard calender. > > Thank you > > "Andrew Lavinsky" wrote: > >> Typically, the system DOES include the Start and End date in the system. >> In your example 4/1 - 4/5, that is three days: Thursday, Friday and >> Monday. >> Do you wish to override the weekends? If so, simply create a new 7 day >> calendar in Tools > Change Working Time and apply to the project and/or >> resources. >> >> Then make sure the settings in Tools > Options > Calendar map to your new >> settings. >> >> - Andrew Lavinsky >> Blog: http://blogs.catapultsystems.com/epm >> >> > Hi When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the >> > project calculates 3 days, I like it to calculate 5 day, which means >> > including the start and end date in duration. How can I set this up. >> > Please help.... >> > >> > Thank you >> > >> >> >> . >>
From: Jim Aksel on 7 Apr 2010 10:46 One other thing to consider. Do not enter dates into Project, let it calculate the dates for you. Use predecessors to link the tasks and move the dates to where they need to be based on their relationships to other tasks. Using the 7 day calendar (and the very busy resource as Steve pointed out), you would establish a start date using a link, then key 5 days .... not 4/1/2010 and 4/5/2010. I know it is off topic, but your post talked about input by date and that got me nervous. Cheers -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "kamran" wrote: > Thank you for the information. I still have a problem setting the newly > created 7-working day calender as a default for my project. My tasks do not > recognize this new setting. My task timeline keeps going back to the > standard calender. > > Thank you > > "Andrew Lavinsky" wrote: > > > Typically, the system DOES include the Start and End date in the system. > > In your example 4/1 - 4/5, that is three days: Thursday, Friday and Monday. > > Do you wish to override the weekends? If so, simply create a new 7 day > > calendar in Tools > Change Working Time and apply to the project and/or resources. > > > > Then make sure the settings in Tools > Options > Calendar map to your new > > settings. > > > > - Andrew Lavinsky > > Blog: http://blogs.catapultsystems.com/epm > > > > > Hi When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the > > > project calculates 3 days, I like it to calculate 5 day, which means > > > including the start and end date in duration. How can I set this up. > > > Please help.... > > > > > > Thank you > > > > > > > > > . > >
|
Pages: 1 Prev: As-built Calendars Next: Print to PDF file |