Prev: Cannot Save Project to Server
Next: Real task duration
From: Tunamonster on 6 May 2010 17:59 I am doing a house remodel and will have some asbestos removed. How do I make it so that there are no other tasks scheduled at the same time as the asbestos abatement? I have tried making a "House" work resource to act as a semaphore but it doesn't seem to mind overscheduling it.
From: Stuart Rosen on 6 May 2010 20:17 This should be as simple as making everything that needs to happen before the asbestos removal a predecessor, and everything that can only start after the asbestos removal a successor of your asbestos removal task. -- Stuart Rosen ------------------------------------------------------------------------ Stuart Rosen's Profile: http://forums.techarena.in/members/199571.htm View this thread: http://forums.techarena.in/microsoft-project/1334597.htm http://forums.techarena.in
From: Prasad on 6 May 2010 21:42 Stuart, What about a task that can be executed either before or after the asbestos removal? Prasad
From: Stuart Rosen on 6 May 2010 22:00 I am not aware of a way that the tool can decide this to you. It's a bit difficult to suggest the best method of dealing with this without knowing more about the project. I'd suggest the project manager needs to plan which of these tasks will most likely be done before the asbestos removal as have the asbestos removal as a successor to these. The tasks that are likely to be done after asbestos removal would have the asbestos removal task as a successor. Depending on the nature of these tasks, you could schedule them to -*be planned *- to run in parallel with the asbestos removal, and then change the relationship once you know when the asbestos removal will actually happen (by splitting those tasks that are already in progress when the asbestos removal starts, or by changing the relationship so that these tasks will only start after asbestos removal). Good luck - this is one where the PM's knowledge will decide the best way of handling it. -- Stuart Rosen ------------------------------------------------------------------------ Stuart Rosen's Profile: http://forums.techarena.in/members/199571.htm View this thread: http://forums.techarena.in/microsoft-project/1334597.htm http://forums.techarena.in
From: Jim Aksel on 7 May 2010 09:35 This is a bit of a challenge to do dynamically. Certainly the "finsh befor abatement" and "Start aftetr abatement" can be handled with appropriate predecessors/successors. There are two issues, tasks in progress may need to be split as they will suspend during the abatement process, and, tasks that may be performed "any" time. More than likely, you will be driven by the availability of your abatement resources. The abatement team will show up at the job site when they complete their prior job and will only give you an estimate of when they can show up. I might consider creating two work calandars. One is a standard work week, the other has the dates when the abatement team will be working set as "non-working time". Assign the calendar with this non-working time to all the tasks except abatement tasks. The abatement tasks use the standard calendar. Now, as the scheduling progressess, the takes will autmomatically schedule themeselves with a down period during abatement. You will need to monitor this closely, if the abatment team notifies you they will start on a different day, then you will have to change the working time of your calendar to accomodate their change. At least you only have to change it in one place. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com "Tunamonster" wrote: > I am doing a house remodel and will have some asbestos removed. How do I make > it so that there are no other tasks scheduled at the same time as the > asbestos abatement? > > I have tried making a "House" work resource to act as a semaphore but it > doesn't seem to mind overscheduling it.
|
Pages: 1 Prev: Cannot Save Project to Server Next: Real task duration |