Prev: Unable to indent/outdent in microsoft project due to circular errors
Next: problems migrating project2k3server data to project2k7server
From: Puppa Romeo Puppa on 5 Oct 2009 11:31 I'm using the 2003 version of Project. I have a number of linked tasks by finish to start, but some of the tasks are not showing the correct start/finish dates. For example a task whose predecessor ends 08/09/09 should begin 08/09/09 but is starting 15/10/09. The constraints are all set to "as soon as possible". I've tried manually amending the date but with no success. Any ideas?
From: Jan De Messemaeker on 5 Oct 2009 11:51 Hi, You definitely mean "unexpected start dates" and not "incorrect" - Project doesn't make that many erors :-) Is your resource leveling set to automatic? Isn't there another predecessor? Isn't there a constraint on the summary ask? Doesn't a resoruce assigned to the tas, have nonworkingtime during the "idle" period? Doesn't the task have a task calendar with nonworking time? Hope this helps, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Puppa Romeo" <Puppa Romeo(a)discussions.microsoft.com> wrote in message news:3DE1B84E-FD44-4D72-982F-614F6AC8D2F8(a)microsoft.com... > I'm using the 2003 version of Project. I have a number of linked tasks by > finish to start, but some of the tasks are not showing the correct > start/finish dates. For example a task whose predecessor ends 08/09/09 > should > begin 08/09/09 but is starting 15/10/09. The constraints are all set to > "as > soon as possible". I've tried manually amending the date but with no > success. > Any ideas?
From: "Steve House" sjhouse at hotmail dot on 5 Oct 2009 11:59 Manually entering a start date resets the constraint to Start No Earlier Than the date entered. Go to the Task Information, Advanced tab and set the constraint back to ASAP if it is something different. Then go to Tools/Options/Calculation and make sure recalculation is set to automatic. "Puppa Romeo" <Puppa Romeo(a)discussions.microsoft.com> wrote in message news:3DE1B84E-FD44-4D72-982F-614F6AC8D2F8(a)microsoft.com... > I'm using the 2003 version of Project. I have a number of linked tasks by > finish to start, but some of the tasks are not showing the correct > start/finish dates. For example a task whose predecessor ends 08/09/09 > should > begin 08/09/09 but is starting 15/10/09. The constraints are all set to > "as > soon as possible". I've tried manually amending the date but with no > success. > Any ideas?
From: Atif Hassan Siddiqui on 7 Oct 2009 08:14 Just double-check resource-leveling is set to manaul. In your case, resource-leveling might seem to be set on automatic.
From: Puppa Romeo on 30 Oct 2009 11:12
Hi all, Firstly, sorry for the delayed response and secondly thanks for your suggestions. The constraints were already set to ASAP and recalculation is set to automatic. There are no lags on the linked tasks and the only non-working days are weekends, which doesn't account for a month delay of the start date. There are no resources currently in the plan therefore automatic resource levelling isn't the problem. I don't think any of these are what is causing the problem, but thanks again for trying to help. |