From: Jonathan on 1 Apr 2010 14:56 1. Our project has a targetted completion of June 30, 2010. 2. For visual purposes, I created a milestone 'Project complete - target June 30, 2010' which has a deadline of June 30 and a 'Must Finish On' June 30 constraint (knowing that this is an inflexible constraint) so that I can visualize the milestone and deadline on the same June 30 date. 3. How do I have indicators appear against tasks that end beyond the targeted project end date? Thanks
From: Jan De Messemaeker on 1 Apr 2010 15:03 Hi, Link the task to the projected end and they will show negative slack (whihc, through a simple formula in a custom field, turn into graphicl indicators) -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message news:D058EDE1-F493-41DC-99AC-6D08AFB29450(a)microsoft.com... > 1. Our project has a targetted completion of June 30, 2010. > 2. For visual purposes, I created a milestone 'Project complete - target > June 30, 2010' which has a deadline of June 30 and a 'Must Finish On' June > 30 > constraint (knowing that this is an inflexible constraint) so that I can > visualize the milestone and deadline on the same June 30 date. > 3. How do I have indicators appear against tasks that end beyond the > targeted project end date? > > Thanks
From: Jonathan on 1 Apr 2010 16:36 To clarify: I want to have each task that finishes or might finish beyond the targetted June 30 project deadline, identified by an indicator in the Indicator column. If I understand you correctly, are saying that I need to link every one of the currently unfinished tasks to the the 'Project complete - target June 30, 2010' deadline 'task'? Also - if you're feeling in a generous mood (!), do you think you might perhaps share with me the formula I need to enter in the customized field? Thanks and kind regards! "Jan De Messemaeker" wrote: > Hi, > Link the task to the projected end and they will show negative slack (whihc, > through a simple formula in a custom field, turn into graphicl indicators) > -- > Jan De Messemaeker > Microsoft Project Most Valuable Professional > +32 495 300 620 > For availability check: > http://users.online.be/prom-ade/Calendar.pdf > "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message > news:D058EDE1-F493-41DC-99AC-6D08AFB29450(a)microsoft.com... > > 1. Our project has a targetted completion of June 30, 2010. > > 2. For visual purposes, I created a milestone 'Project complete - target > > June 30, 2010' which has a deadline of June 30 and a 'Must Finish On' June > > 30 > > constraint (knowing that this is an inflexible constraint) so that I can > > visualize the milestone and deadline on the same June 30 date. > > 3. How do I have indicators appear against tasks that end beyond the > > targeted project end date? > > > > Thanks
From: Trevor Rabey on 1 Apr 2010 21:22 Jan is always very generous but you can easily do this yourself. After you link the task to the nailed-down finish milestone you will want to see if the task has negative slack. Switch to the Schedule Table. Use Tools, Customize Fields to use a spare field, Rename it, make the formula, and set up the graphics. The formula that you put in a spare (flag) field will be something like IIF([Total Slack] < 0,yes,no). Then set up the graphical indicators. You can't use the Indicators column because it is reserved for whatever MSP uses it for. BTW, putting hard date constraints and deadlines on milestones which have predecessors which end up with negative slack is a nightmarish contradiction of all best practice critical path modeling, and will cause a lot of frustration and interpretation difficulties. I can explain how to do it but I don't recommend it. Guys, bit of support here? -- Trevor Rabey 0407213955 61 8 92727485 PERFECT PROJECT PLANNING www.perfectproject.com.au "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message news:161655CF-1E72-4E52-A1F2-5BCCC7D8EA67(a)microsoft.com... > To clarify: I want to have each task that finishes or might finish beyond > the > targetted June 30 project deadline, identified by an indicator in the > Indicator column. If I understand you correctly, are saying that I need > to > link every one of the currently unfinished tasks to the the 'Project > complete > - target June 30, 2010' deadline 'task'? > > Also - if you're feeling in a generous mood (!), do you think you might > perhaps share with me the formula I need to enter in the customized field? > > Thanks and kind regards! > > > > "Jan De Messemaeker" wrote: > >> Hi, >> Link the task to the projected end and they will show negative slack >> (whihc, >> through a simple formula in a custom field, turn into graphicl >> indicators) >> -- >> Jan De Messemaeker >> Microsoft Project Most Valuable Professional >> +32 495 300 620 >> For availability check: >> http://users.online.be/prom-ade/Calendar.pdf >> "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message >> news:D058EDE1-F493-41DC-99AC-6D08AFB29450(a)microsoft.com... >> > 1. Our project has a targetted completion of June 30, 2010. >> > 2. For visual purposes, I created a milestone 'Project complete - >> > target >> > June 30, 2010' which has a deadline of June 30 and a 'Must Finish On' >> > June >> > 30 >> > constraint (knowing that this is an inflexible constraint) so that I >> > can >> > visualize the milestone and deadline on the same June 30 date. >> > 3. How do I have indicators appear against tasks that end beyond the >> > targeted project end date? >> > >> > Thanks
From: Jan De Messemaeker on 2 Apr 2010 01:57
Hi Trevor, Theory of constraints is by no means a nightmarish project management method. And according to several users it leads to success rather than frustration. Fixed deadlines are an every day's reality and IMHO more important that original estimations or the plan at hand. Greetings, -- Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http://users.online.be/prom-ade/Calendar.pdf "Trevor Rabey" <trevorATperfectproject.com.au> wrote in message news:Qe2dnXwc0tZX2yjWnZ2dnUVZ8uqdnZ2d(a)westnet.com.au... > Jan is always very generous but you can easily do this yourself. > After you link the task to the nailed-down finish milestone you will want > to see if the task has negative slack. > Switch to the Schedule Table. > Use Tools, Customize Fields to use a spare field, Rename it, make the > formula, and set up the graphics. > The formula that you put in a spare (flag) field will be something like > IIF([Total Slack] < 0,yes,no). > Then set up the graphical indicators. > > You can't use the Indicators column because it is reserved for whatever > MSP uses it for. > > BTW, putting hard date constraints and deadlines on milestones which have > predecessors which end up with negative slack is a nightmarish > contradiction of all best practice critical path modeling, and will cause > a lot of frustration and interpretation difficulties. > I can explain how to do it but I don't recommend it. > Guys, bit of support here? > -- > Trevor Rabey > 0407213955 > 61 8 92727485 > PERFECT PROJECT PLANNING > www.perfectproject.com.au > > "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message > news:161655CF-1E72-4E52-A1F2-5BCCC7D8EA67(a)microsoft.com... >> To clarify: I want to have each task that finishes or might finish beyond >> the >> targetted June 30 project deadline, identified by an indicator in the >> Indicator column. If I understand you correctly, are saying that I need >> to >> link every one of the currently unfinished tasks to the the 'Project >> complete >> - target June 30, 2010' deadline 'task'? >> >> Also - if you're feeling in a generous mood (!), do you think you might >> perhaps share with me the formula I need to enter in the customized >> field? >> >> Thanks and kind regards! >> >> >> >> "Jan De Messemaeker" wrote: >> >>> Hi, >>> Link the task to the projected end and they will show negative slack >>> (whihc, >>> through a simple formula in a custom field, turn into graphicl >>> indicators) >>> -- >>> Jan De Messemaeker >>> Microsoft Project Most Valuable Professional >>> +32 495 300 620 >>> For availability check: >>> http://users.online.be/prom-ade/Calendar.pdf >>> "Jonathan" <Jonathan(a)discussions.microsoft.com> wrote in message >>> news:D058EDE1-F493-41DC-99AC-6D08AFB29450(a)microsoft.com... >>> > 1. Our project has a targetted completion of June 30, 2010. >>> > 2. For visual purposes, I created a milestone 'Project complete - >>> > target >>> > June 30, 2010' which has a deadline of June 30 and a 'Must Finish On' >>> > June >>> > 30 >>> > constraint (knowing that this is an inflexible constraint) so that I >>> > can >>> > visualize the milestone and deadline on the same June 30 date. >>> > 3. How do I have indicators appear against tasks that end beyond the >>> > targeted project end date? >>> > >>> > Thanks > > |