From: on
I am working in MS Project 2007. I am using the standard calendar, but I
have changed the working times to 7:30 am to 11:30 am and 12:30 pm to 4:30
pm, which is equivalent to 8 hours. When I list my tasks and I have a task
that is 1 day the start and finish shows Monday to Tuesday, which is 2 days.
I went back to change the working time to standard 8-5, and then the start
and finish day for a 1 day duration read Monday to Monday, which is correct.
Why aren't my new working hours working?
From: JulieS on
Hello T�,

In addition to Mike's great advice, I suggest turning on the display
of your dates to show date and time through Tools > Options, View
tab.

It's likely the default start time of your Project is 08:00 which is
causing the 1 day duration (8 working hours) to roll over to the
next day.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"T�" <T(a)discussions.microsoft.com> wrote in message
news:E78F4C26-F8BA-4D5C-9015-72A2E9AB05DD(a)microsoft.com...
>I am working in MS Project 2007. I am using the standard calendar,
>but I
> have changed the working times to 7:30 am to 11:30 am and 12:30 pm
> to 4:30
> pm, which is equivalent to 8 hours. When I list my tasks and I
> have a task
> that is 1 day the start and finish shows Monday to Tuesday, which
> is 2 days.
> I went back to change the working time to standard 8-5, and then
> the start
> and finish day for a 1 day duration read Monday to Monday, which
> is correct.
> Why aren't my new working hours working?