Prev: Hinding/Deleating Resource information before sending
Next: Linking Access 2007 to Microsoft Project 2007
From: CamJam on 19 Jan 2010 11:48 I really appreciate the help. I like both ways that you all have suggested. I'm actually using both WBS and Customized Fields. I guess the problem I'm having is how to determine the total cost on the project based on % complete for that particular item, in this example Grade. I guess I can't view that on the Gantt I just have to do it via a report? If it's via a report how do I do this? Thank you both, Cameron -- CamJam ------------------------------------------------------------------------ CamJam's Profile: http://forums.techarena.in/members/175542.htm View this thread: http://forums.techarena.in/microsoft-project/1294086.htm http://forums.techarena.in
From: Andrew Lavinsky on 19 Jan 2010 12:50 If I follow you correctly, you could track Actual Cost for each task, which will be a % of the overall task cost. When you group by Grade, it should sum up the field - so you can subtotal for each grouped element. That's what grouping is for - subtotals. - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > I really appreciate the help. I like both ways that you all have > suggested. I'm actually using both WBS and Customized Fields. I guess > the problem I'm having is how to determine the total cost on the > project based on % complete for that particular item, in this example > Grade. I guess I can't view that on the Gantt I just have to do it via > a report? If it's via a report how do I do this? > > Thank you both, > Cameron > http://forums.techarena.in >
From: CamJam on 20 Jan 2010 11:04 Just lost my post! Recap. Preface: Thank you for your replies. I'm having problems generating reports based on my WBS. Example, let's say my tasks are as follows (WBS in parenthesis): Section 1 (1) Clearing (1.1) Grade (1.2) Install Pipe (1.3) Section 2 (2) Clearing (2.1) Grade (2.2) Install Pipe (2.3) Section 3 (3) Clearing (3.1) Grade (3.2) Install Pipe (3.3) Is there anyway to do a report using WBS instead of task names, that way I can get a total actual cost or % complete for Clearing,Grade, Or Install on the whole project. Is Visio the option (I don't have it but I hear you can do reports using WBS)? In addition let's say their are subtasks for these. Can I generate a report only using X.X instead of WBS X.X.X? I've tried custom reporting but am not seeing a selection for WBS in lieu of task names I just see where I can sort via WBS. Thank you, Cam -- CamJam ------------------------------------------------------------------------ CamJam's Profile: http://forums.techarena.in/members/175542.htm View this thread: http://forums.techarena.in/microsoft-project/1294086.htm http://forums.techarena.in
From: Rob Schneider on 20 Jan 2010 11:52 The way I would do it is as Andrew suggested previously ... use Groups. Add a custom text field called "Phase" and for each task assign it to Clearing, Grading, or Installing. Then group by that field (Menu: Project: Group By, More groups, New, and make it group by the new custom text field. Project will rollup sumary totals and % complete and all that for you. I'm not sure what you mean by the second question, but perhaps if you mess around a little bit with grouping you'll find a way to meet your needs. --rms www.rmschneider.com On 20/01/10 16:04, CamJam wrote: > Just lost my post! > > Recap. > > Preface: Thank you for your replies. > > I'm having problems generating reports based on my WBS. > > Example, let's say my tasks are as follows (WBS in parenthesis): > > Section 1 (1) > Clearing (1.1) > Grade (1.2) > Install Pipe (1.3) > > Section 2 (2) > Clearing (2.1) > Grade (2.2) > Install Pipe (2.3) > > Section 3 (3) > Clearing (3.1) > Grade (3.2) > Install Pipe (3.3) > > Is there anyway to do a report using WBS instead of task names, that > way I can get a total actual cost or % complete for Clearing,Grade, Or > Install on the whole project. > > Is Visio the option (I don't have it but I hear you can do reports > using WBS)? > > In addition let's say their are subtasks for these. Can I generate a > report only using X.X instead of WBS X.X.X? > > I've tried custom reporting but am not seeing a selection for WBS in > lieu of task names I just see where I can sort via WBS. > > Thank you, > Cam > >
First
|
Prev
|
Pages: 1 2 Prev: Hinding/Deleating Resource information before sending Next: Linking Access 2007 to Microsoft Project 2007 |