From: aclaar877 on

I am having a problem with MSProject moving task end dates way out into
the future, even though I haven't changed duration, nor have I resource
leveled the task. For example, an 80-hour task, fixed work, 75%
complete, with resources working full time ends up with an end date
getting kicked out several months. It's not a predecessor problem.
This usually happens when I've updated resource loading or pasted a task
into the project from another project. Regardless, the end date makes
no sense. Any advice as to what is going on here?


--
aclaar877
------------------------------------------------------------------------
aclaar877's Profile: http://forums.techarena.in/members/174269.htm
View this thread: http://forums.techarena.in/microsoft-project/1293246.htm

http://forums.techarena.in

From: Sai on
On Jan 15, 2:36 am, aclaar877 <aclaar877.44s...(a)DoNotSpam.com> wrote:
> I am having a problem with MSProject moving task end dates way out into
> the future, even though I haven't changed duration, nor have I resource
> leveled the task.  For example, an 80-hour task, fixed work, 75%
> complete, with resources working full time ends up with an end date
> getting kicked out several months.  It's not a predecessor problem.
> This usually happens when I've updated resource loading or pasted a task
> into the project from another project.  Regardless, the end date makes
> no sense.  Any advice as to what is going on here?
>
> --
> aclaar877
> ------------------------------------------------------------------------
> aclaar877's Profile:http://forums.techarena.in/members/174269.htm
> View this thread:http://forums.techarena.in/microsoft-project/1293246.htm
>
> http://forums.techarena.in

It looks like after recording the actuals for tasks, its finish date
gets unrealistic. By default, when you enter progress as percent
complete or total work to date, Project uses the status date to
determine where to place actual work and where to schedule remaining
work.

Please check the following settings in project:
a) Choose Project | Project Information and validate if the Status
date field is proper.
b) Choose Tools | Options ... | Calculations tab. Validate the
following checkboxes
- Move end of completed parts after status date back to status date
- Move start of remaining parts before status date forward to status
date

Let me know if this helps