From: Michozzy on
Hi, I am getting ready to marry up two schedules (around 6000 task lines) and
am trying to find a potentially quicker solution than what I have planned
(just in case plan A doesn't go so well for me).

Two months ago I took a copy of my master file and began to add much needed
work into it, however it was not yet authorized work, so I had to continue
providing status into the main master file up to this point in time.

Now that the work will be authorized in May, I need to take the current
master file, and make sure all of the "what-if" modifications from the
secondary file get into it. I am planning to have a partner help me with
this, as my second set of eyes. Would you guess that the easiest way to do
this would be to literally go line by line to make sure we get all of the
"revised" logic in? The UIDs are not a one-for-one deal (in other words, many
task name changes, cost changes, logic changes, etc) have switched around in
my "what-if". Are there any suggestions for an easier way to compare the two
files?

I am well aware of the file-compare tool, and my company has created a more
sophisticated bolt-on version of it, but other than that, any other
suggestions to make sure we don't waste too much precious time?

We have about eight days to conquer this beast. Thanks so much!

From: Rod Gill on
If the Unique IDs have remained the same, then VBA code could quickly update
task names, and resource assignments etc. If Unique IDs have changed you
could try inserting a custom Number and entering the Unique ID of the same
task in the other file and again have a VBA macro to read task data using
the ID in the number field. This would be easy and straight forward for
anyone with basic VBA skills (or talk to me!).

Essentially for any kind of successful merger there has to be a common field
for Project or a VBA macro to use. If you don't have a reliable merge field
it's probably back to the old mark 1 manual methods and I don't envy you
that for 6,000 tasks!

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




"Michozzy" <Michozzy(a)discussions.microsoft.com> wrote in message
news:DDCBF777-F0EC-4F32-B282-18F01366BA56(a)microsoft.com...
> Hi, I am getting ready to marry up two schedules (around 6000 task lines)
> and
> am trying to find a potentially quicker solution than what I have planned
> (just in case plan A doesn't go so well for me).
>
> Two months ago I took a copy of my master file and began to add much
> needed
> work into it, however it was not yet authorized work, so I had to continue
> providing status into the main master file up to this point in time.
>
> Now that the work will be authorized in May, I need to take the current
> master file, and make sure all of the "what-if" modifications from the
> secondary file get into it. I am planning to have a partner help me with
> this, as my second set of eyes. Would you guess that the easiest way to do
> this would be to literally go line by line to make sure we get all of the
> "revised" logic in? The UIDs are not a one-for-one deal (in other words,
> many
> task name changes, cost changes, logic changes, etc) have switched around
> in
> my "what-if". Are there any suggestions for an easier way to compare the
> two
> files?
>
> I am well aware of the file-compare tool, and my company has created a
> more
> sophisticated bolt-on version of it, but other than that, any other
> suggestions to make sure we don't waste too much precious time?
>
> We have about eight days to conquer this beast. Thanks so much!
>
>
> __________ Information from ESET Smart Security, version of virus
> signature database 5063 (20100426) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>

__________ Information from ESET Smart Security, version of virus signature database 5063 (20100426) __________

The message was checked by ESET Smart Security.

http://www.eset.com