From: Junada0 on 11 Jan 2010 11:32 Project 2007 - Date move question. First post on this forum, would appreciate any help RE: Project move - all tasks Is there a simple method to move all dates in a project plan forward by a given number of days, say 1 week, 1 month etc. So that *all* the dates move forward or indeed backwards if required. Many thanks -- Junada0 ------------------------------------------------------------------------ Junada0's Profile: http://forums.techarena.in/members/173121.htm View this thread: http://forums.techarena.in/microsoft-project/1292080.htm http://forums.techarena.in
From: JulieS on 11 Jan 2010 12:28 Hello Junada0, If you need to move the start date of an entire project, choose Project > Project Information and supply a new start date to the project. If the tasks are appropriately linked (predecessor and successor relationships set) and have not been constrained, then all the tasks should move without trouble. If you have set constraints other than ASAP and need to move constrained tasks, show the Analysis toolbar and click the "Adjust Dates" button. The button will adjust all tasks relative to the initial start date. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 1/11/2010 11:32 AM, Junada0 wrote: > Project 2007 - Date move question. > > First post on this forum, would appreciate any help > > RE: Project move - all tasks > > Is there a simple method to move all dates in a project plan forward by > a given number of days, say 1 week, 1 month etc. > > So that *all* the dates move forward or indeed backwards if required. > > Many thanks > > >
|
Pages: 1 Prev: Calculations don't work Next: Date 1 field not updating automatically |