From: Naga on 13 Mar 2010 18:38 Hi, I have a baseline plan which has two phases (initial and final). Few tasks in the initial phase are not done due to the non-availability of planned resources. Final phase is planned to start from next week and please let me know how to move those tasks from initial to final phase. Regards Naga
From: Rob Schneider on 14 Mar 2010 03:31
What is it you did you distinguish in Project the difference between the initial and final phases? What "barrier" is stopping uncompleted work moving forward when you update the schedule with progress? Perhaps you have constraints on the tasks in the initial phase (anything other than "as soon as possible")? --rms www.rmschneider.com On 13/03/10 23:38, Naga wrote: > Hi, > > I have a baseline plan which has two phases (initial and final). Few tasks > in the initial phase are not done due to the non-availability of planned > resources. Final phase is planned to start from next week and please let me > know how to move those tasks from initial to final phase. > > Regards > Naga |