From: Naga on
Hi,

I have a baseline plan which has two phases (initial and final). Few tasks
in the initial phase are not done due to the non-availability of planned
resources. Final phase is planned to start from next week and please let me
know how to move those tasks from initial to final phase.

Regards
Naga
From: Rob Schneider on
What is it you did you distinguish in Project the difference between the
initial and final phases? What "barrier" is stopping uncompleted work
moving forward when you update the schedule with progress?

Perhaps you have constraints on the tasks in the initial phase (anything
other than "as soon as possible")?


--rms

www.rmschneider.com




On 13/03/10 23:38, Naga wrote:
> Hi,
>
> I have a baseline plan which has two phases (initial and final). Few tasks
> in the initial phase are not done due to the non-availability of planned
> resources. Final phase is planned to start from next week and please let me
> know how to move those tasks from initial to final phase.
>
> Regards
> Naga