From: player on 24 May 2010 19:47 I'm using MS Project 2007, have several task linked with finish to start. I have set date to schedule from, hours per day set to 8 and Working Monday thru Friday. My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10 Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this? Thanks in advance for your help.
From: JulieS on 24 May 2010 20:00 Player, Turn on the display of time. Tools > Options, View tab and select a format that shows time as well as date. That may help figure out what is going on. You mention that you have the standard setting hours per day of 8. Have you modified the calendar in Tools > Change Working time? I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/24/2010 7:47 PM, player wrote: > I'm using MS Project 2007, have several task linked with finish to start. I > have set date to schedule from, hours per day set to 8 and Working Monday > thru Friday. > > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10 > > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this? > > Thanks in advance for your help. >
From: player on 24 May 2010 20:57 ok display of time shows start 8am and Finish 8am on the next day for a 1 Day duration task and yes I have modified the calendar in Tools >options, calender Tab to 7:00am to 12:00pm 12:30pm to 3:30pm Start dates still show starting on same date as predecessors finish Date Dont know why start time is 8am and finish time is 8am on next day for 1 day task? "JulieS" wrote: > Player, > > Turn on the display of time. Tools > Options, View tab and > select a format that shows time as well as date. That may help > figure out what is going on. > > You mention that you have the standard setting hours per day of > 8. Have you modified the calendar in Tools > Change Working time? > > I hope this helps. Let us know how you get along. > > Julie > Project MVP > > Visit http://project.mvps.org/ for the FAQs and additional > information about Microsoft Project > > On 5/24/2010 7:47 PM, player wrote: > > I'm using MS Project 2007, have several task linked with finish to start. I > > have set date to schedule from, hours per day set to 8 and Working Monday > > thru Friday. > > > > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 > > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10 > > > > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this? > > > > Thanks in advance for your help. > > > . >
From: player on 24 May 2010 22:03 OK what I did was made a new schedule using project default calender and working times and all is good for now. I would like to change working time from 7am to 3:30pm with 1/2 hour lunch from 12 to 12:30 but I need to submitt this in the AM. so I just turned off view times for now. Thanks for your help "player" wrote: > ok display of time shows start 8am and Finish 8am on the next day for a 1 Day > duration task > > and yes I have modified the calendar in Tools >options, calender Tab to > 7:00am to 12:00pm 12:30pm to 3:30pm > > Start dates still show starting on same date as predecessors finish Date > > Dont know why start time is 8am and finish time is 8am on next day for 1 day > task? > > "JulieS" wrote: > > > Player, > > > > Turn on the display of time. Tools > Options, View tab and > > select a format that shows time as well as date. That may help > > figure out what is going on. > > > > You mention that you have the standard setting hours per day of > > 8. Have you modified the calendar in Tools > Change Working time? > > > > I hope this helps. Let us know how you get along. > > > > Julie > > Project MVP > > > > Visit http://project.mvps.org/ for the FAQs and additional > > information about Microsoft Project > > > > On 5/24/2010 7:47 PM, player wrote: > > > I'm using MS Project 2007, have several task linked with finish to start. I > > > have set date to schedule from, hours per day set to 8 and Working Monday > > > thru Friday. > > > > > > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 > > > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10 > > > > > > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this? > > > > > > Thanks in advance for your help. > > > > > . > >
From: JulieS on 25 May 2010 05:45 You're welcome player. You can certainly change the working time in Tools> Change working time. As Mike Glen, notes in the reference to the FAQ, the working time needs to be modified as you did, but you also need to change he default start and end time as well in Tools > Options, Calendar. Also check the start time of your project in Project > Project Information. My guess is your project starts at 8:00 not 7:00 -- thus the finish at 8:00 the next day. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 5/24/2010 10:03 PM, player wrote: > OK what I did was made a new schedule using project default calender and > working times and all is good for now. > > I would like to change working time from 7am to 3:30pm with 1/2 hour lunch > from 12 to 12:30 but I need to submitt this in the AM. so I just turned off > view times for now. > > Thanks for your help > > "player" wrote: > >> ok display of time shows start 8am and Finish 8am on the next day for a 1 Day >> duration task >> >> and yes I have modified the calendar in Tools>options, calender Tab to >> 7:00am to 12:00pm 12:30pm to 3:30pm >> >> Start dates still show starting on same date as predecessors finish Date >> >> Dont know why start time is 8am and finish time is 8am on next day for 1 day >> task? >> >> "JulieS" wrote: >> >>> Player, >>> >>> Turn on the display of time. Tools> Options, View tab and >>> select a format that shows time as well as date. That may help >>> figure out what is going on. >>> >>> You mention that you have the standard setting hours per day of >>> 8. Have you modified the calendar in Tools> Change Working time? >>> >>> I hope this helps. Let us know how you get along. >>> >>> Julie >>> Project MVP >>> >>> Visit http://project.mvps.org/ for the FAQs and additional >>> information about Microsoft Project >>> >>> On 5/24/2010 7:47 PM, player wrote: >>>> I'm using MS Project 2007, have several task linked with finish to start. I >>>> have set date to schedule from, hours per day set to 8 and Working Monday >>>> thru Friday. >>>> >>>> My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10 >>>> Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10 >>>> >>>> Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this? >>>> >>>> Thanks in advance for your help. >>>> >>> . >>>
|