From: Michael T on
Many eons ago using an early version of Project, I could enter tasks of 30, 45,
60, 75 days, etc., duration to mean a month, month-and-a-half, etc., and the
program understood I meant for these time blocks to span non-working days
(weekends); so for example, a "30-day" task entered on May 1 would finish June 1.

Fast-forward to the present day, and my Project 2007 interprets "30 days" to
mean 30 *work* days rather than 30 calendar days.

How can I use 30/45/60/75 etc., again and get the durations I used to? A few
googlings hinted this'd be a setting in Tools> Options, but nothing there jumps
out.

Grateful for any clues or pointers to a good newbie FAQ.

Michael
From: Sai on
On Jan 12, 9:40 am, Michael T <chilledmonkeybrains...(a)gmail.com>
wrote:
> Many eons ago using an early version of Project, I could enter tasks of 30, 45,
> 60, 75 days, etc., duration to mean a month, month-and-a-half, etc., and the
> program understood I meant for these time blocks to span non-working days
> (weekends); so for example, a "30-day" task entered on May 1 would finish June 1.
>
> Fast-forward to the present day, and my Project 2007 interprets "30 days" to
> mean 30 *work* days rather than 30 calendar days.
>
> How can I use 30/45/60/75 etc., again and get the durations I used to? A few
> googlings hinted this'd be a setting in Tools> Options, but nothing there jumps
> out.
>
> Grateful for any clues or pointers to a good newbie FAQ.
>
> Michael

Michael -

To enter calendar days, you need go for elapsed days. Elapsed days
ignores the distinction between working and non working time on
calendars. So, instead of entering 30 days, type 30 edays.

Refer: http://alturl.com/wcg5

Please let us know if this helps

- Sai, PMP, PMI-SP, MCTS, MCT
http://saipower.wordpress.com
From: Trevor Rabey on
You're not pulling our legs are you?
An eon is a long time, certainly back to sometime before software existed.
You need to recalibrate your fuzzy recollection of how you think you
remember it working eons ago, and your expectations of how MSP works now.
Probably best to forget about the recollections and expectations and focus
on here and now.

30 days has never been a calendar month and duration has always been working
days as defined in the project calendar (or the task calendar if there is
one).

In Tools, Options, Calendar, the default is 1 month = 20 days (that's
working days).
This means that if you input 1 month as a duration, MSP converts it to 20
working days.
You can change it but it is better not to mess with it and just input
duration in days.

If you input 45 days, the bar in the Gantt Chart runs through the
non-working days but they aren't counted in the 45.
The finish date falls wherever it falls, not on a particular date of a
particular month.

Suggestion: do not pursue your line of thinking on this or you will be
annoyed and frustrated.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Michael T" <chilledmonkeybrains100(a)gmail.com> wrote in message
news:OHXPyF0kKHA.3792(a)TK2MSFTNGP02.phx.gbl...
>
> Many eons ago using an early version of Project, I could enter tasks of
> 30, 45, 60, 75 days, etc., duration to mean a month, month-and-a-half,
> etc., and the program understood I meant for these time blocks to span
> non-working days (weekends); so for example, a "30-day" task entered on
> May 1 would finish June 1.
>
> Fast-forward to the present day, and my Project 2007 interprets "30 days"
> to mean 30 *work* days rather than 30 calendar days.
>
> How can I use 30/45/60/75 etc., again and get the durations I used to? A
> few googlings hinted this'd be a setting in Tools> Options, but nothing
> there jumps out.
>
> Grateful for any clues or pointers to a good newbie FAQ.
>
> Michael


From: Trevor Rabey on
Suggestion #2: if you don't want spambots to harvest your email address so
that every huckster on the planet can send you junk advertising, don't use
it when posting in newsgroups. Disguise it somehow, like:

chilledmonkeybrains100AT - don't spam - gmail.com

--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au

"Michael T" <chilledmonkeybrains100(a)gmail.com> wrote in message
news:OHXPyF0kKHA.3792(a)TK2MSFTNGP02.phx.gbl...
>
> Many eons ago using an early version of Project, I could enter tasks of
> 30, 45, 60, 75 days, etc., duration to mean a month, month-and-a-half,
> etc., and the program understood I meant for these time blocks to span
> non-working days (weekends); so for example, a "30-day" task entered on
> May 1 would finish June 1.
>
> Fast-forward to the present day, and my Project 2007 interprets "30 days"
> to mean 30 *work* days rather than 30 calendar days.
>
> How can I use 30/45/60/75 etc., again and get the durations I used to? A
> few googlings hinted this'd be a setting in Tools> Options, but nothing
> there jumps out.
>
> Grateful for any clues or pointers to a good newbie FAQ.
>
> Michael


From: spamboy6547 on
On Tue, 12 Jan 2010 13:20:12 +0800, Trevor Rabey wrote:

> You're not pulling our legs are you?
> An eon is a long time, certainly back to sometime before software existed.
> You need to recalibrate your fuzzy recollection of how you think you
> remember it working eons ago, and your expectations of how MSP works now.
> Probably best to forget about the recollections and expectations and focus
> on here and now.
>
> 30 days has never been a calendar month and duration has always been working
> days as defined in the project calendar (or the task calendar if there is
> one).
>
> In Tools, Options, Calendar, the default is 1 month = 20 days (that's
> working days).
> This means that if you input 1 month as a duration, MSP converts it to 20
> working days.
> You can change it but it is better not to mess with it and just input
> duration in days.
>
> If you input 45 days, the bar in the Gantt Chart runs through the
> non-working days but they aren't counted in the 45.
> The finish date falls wherever it falls, not on a particular date of a
> particular month.
>
> Suggestion: do not pursue your line of thinking on this or you will be
> annoyed and frustrated.

In addition to Trevor's good advice, I'll add a word or two of my own.

A widely accepted heuristic in Project Scheduling is that tasks should be
between 1 day and 10 days in length. Why? Shorter tasks are microplanning
and will drive you crazy trying to track them all. Longer ones give
resources the opportunity to blow out your schedule. What happens if at the
end of 60 days on a critical task, you find out nothing has been
accomplished? You're now 3 months behind schedule. It happens.

You need a deliverable at least every 10 working days, if not more. That
way, you know where you are. Unless of course, you trust every resource to
never mislead you on progress reporting. In which case, you have much, much
bigger problems than how M$ Project interprets durations!

Hope this helps.