From: el00guapo on 12 Jan 2010 17:51 I'm trying to use the resource "group" field to further detail resource capabilities/competencies. As such, there are of course multi-talented people that fit into two or more competencies. Is there a way to assign a resource to multiple groups? Ideally, when looking at the resource sheet and grouping by "resource group" I would then see some resources twice. Thanks in advance for your help & advice.
From: Andrew Lavinsky on 12 Jan 2010 19:39
The only way to achieve what you want is to have two different resources representing different skill sets but the same person. Most people just create a custom field, tie it to a lookup table, and use that to capture multiple skill sets - or you can create a task custom field with the same specs and assign it at the assignment level for data mining. Why are you trying to do this exactly? - Andrew Lavinsky Blog: http://blogs.catapultsystems.com/epm > I'm trying to use the resource "group" field to further detail > resource capabilities/competencies. As such, there are of course > multi-talented people that fit into two or more competencies. > > Is there a way to assign a resource to multiple groups? Ideally, when > looking at the resource sheet and grouping by "resource group" I would > then see some resources twice. > > Thanks in advance for your help & advice. > |