From: Greg on
I see this in the help file.
How can I view this field?
If I select insert column, I cannot find the Pessimistic Duration field.
thanks


Pessimistic Duration (task field) The Pessimistic Duration field
contains the worst-case possibility for the total span of active working
time expected for a task, that is, the time from the pessimistic start to
the pessimistic finish of a task. You can enter this date as part of a PERT
analysis calculation.

From: Rod Gill on
If you display the Analysis Toolbar, then click the PERT Analysis button it
displays a PERT Toolbar. On here is a Pessimistic Gantt that re-uses
Duration3 for pessimistic durations. The PERT Entry sheet button is where
you enter the data.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




"Greg" <greg(a)nospam.com> wrote in message
news:OJhdR2E3KHA.4752(a)TK2MSFTNGP02.phx.gbl...
> I see this in the help file.
> How can I view this field?
> If I select insert column, I cannot find the Pessimistic Duration field.
> thanks
>
>
> Pessimistic Duration (task field) The Pessimistic Duration field
> contains the worst-case possibility for the total span of active working
> time expected for a task, that is, the time from the pessimistic start to
> the pessimistic finish of a task. You can enter this date as part of a
> PERT analysis calculation.
>
>
> __________ Information from ESET Smart Security, version of virus
> signature database 5029 (20100414) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>

__________ Information from ESET Smart Security, version of virus signature database 5029 (20100414) __________

The message was checked by ESET Smart Security.

http://www.eset.com



 | 
Pages: 1
Prev: Recurring Export?
Next: resource and gantt views