From: PS on 24 Sep 2006 22:33 Can anyone help me with this. The plan is baselined. The status date is today. I have actual costs, and physical % complete. BAC and EAC are calcuated. BCWS is calcuated, however BCWP is zero. I checked both the project as well as the task Earned Value calculation is Physical % percent complete. Can anyone help? Appreciate very much.
From: Steve House on 25 Sep 2006 06:18 Have you manually entered the % Physical Complete estimates? Remember, simply entering a % Complete using the tracking toolbar or the Update Project menu tools will not update the % Physical complete automatically, you have to do that for each task in the project by hand. -- Steve House [Project MVP] MS Project Trainer & Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "PS" <PS(a)discussions.microsoft.com> wrote in message news:B7DCB53D-2C8C-41B1-A677-E554FE33E18F(a)microsoft.com... > Can anyone help me with this. The plan is baselined. The status date is > today. I have actual costs, and physical % complete. BAC and EAC are > calcuated. BCWS is calcuated, however BCWP is zero. > > I checked both the project as well as the task Earned Value calculation is > Physical % percent complete. > > Can anyone help? Appreciate very much.
|
Pages: 1 Prev: Microsoft project Next: Project File Corruption |