From: Roger on 27 Jan 2006 17:43 I want print out the gant chart without saturday and sunday to maximize the days printed.
From: John on 27 Jan 2006 20:59 In article <C0B7A57B-5B4E-46E6-A9BF-81C0D8A6CDD5(a)microsoft.com>, "Roger" <Roger(a)discussions.microsoft.com> wrote: > I want print out the gant chart without saturday and sunday to maximize the > days printed. Roger, Sorry, that is not an option for Project when viewing or printing the Gantt display. John Project MVP
|