From: smw on
I need to have a separate line item in my plan for the lead-times on several
purchases. Example: order is placed on 6/30/2010, lead time to delivery is
60 calendar days, delivery would be on 8/28/2010. To do this I created a
lead-time calendar that makes every day a work day by setting all days to
8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
LeadTime is assigned to the task, no resources specified.

The problem; project computes the Planned End Date at 8/22/2010 which by my
calculation is 7 days short of 60. Changing the calendar attached to this
task to the 24hour one increases the discrepancy.

Any suggestions will of course be greatly appreciated.

Steven Wheeler
From: JulieS on
Hello Steven Wheeler,

Assuming that your project is set to a "day" equals 8 hours, the
9 hour day on Saturday and Sunday could explain the discrepancy.
Change your "Leadtime" calendar to 8:00 - 4:00 pm with no lunch
time and you should be all set.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/12/2010 12:38 PM, smw wrote:
> I need to have a separate line item in my plan for the lead-times on several
> purchases. Example: order is placed on 6/30/2010, lead time to delivery is
> 60 calendar days, delivery would be on 8/28/2010. To do this I created a
> lead-time calendar that makes every day a work day by setting all days to
> 8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
> LeadTime is assigned to the task, no resources specified.
>
> The problem; project computes the Planned End Date at 8/22/2010 which by my
> calculation is 7 days short of 60. Changing the calendar attached to this
> task to the 24hour one increases the discrepancy.
>
> Any suggestions will of course be greatly appreciated.
>
> Steven Wheeler
From: smw on
That did the trick, thank you!
What a nuckle-headed mistake on my part.

"JulieS" wrote:

> Hello Steven Wheeler,
>
> Assuming that your project is set to a "day" equals 8 hours, the
> 9 hour day on Saturday and Sunday could explain the discrepancy.
> Change your "Leadtime" calendar to 8:00 - 4:00 pm with no lunch
> time and you should be all set.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
>
> On 5/12/2010 12:38 PM, smw wrote:
> > I need to have a separate line item in my plan for the lead-times on several
> > purchases. Example: order is placed on 6/30/2010, lead time to delivery is
> > 60 calendar days, delivery would be on 8/28/2010. To do this I created a
> > lead-time calendar that makes every day a work day by setting all days to
> > 8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
> > LeadTime is assigned to the task, no resources specified.
> >
> > The problem; project computes the Planned End Date at 8/22/2010 which by my
> > calculation is 7 days short of 60. Changing the calendar attached to this
> > task to the 24hour one increases the discrepancy.
> >
> > Any suggestions will of course be greatly appreciated.
> >
> > Steven Wheeler
> .
>
From: JulieS on
You're most welcome and don't be too hard on yourself. Project
has a lot of moving parts and sometimes we forget to keep them
synchronized.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/12/2010 2:11 PM, smw wrote:
> That did the trick, thank you!
> What a nuckle-headed mistake on my part.
>
> "JulieS" wrote:
>
>> Hello Steven Wheeler,
>>
>> Assuming that your project is set to a "day" equals 8 hours, the
>> 9 hour day on Saturday and Sunday could explain the discrepancy.
>> Change your "Leadtime" calendar to 8:00 - 4:00 pm with no lunch
>> time and you should be all set.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>> On 5/12/2010 12:38 PM, smw wrote:
>>> I need to have a separate line item in my plan for the lead-times on several
>>> purchases. Example: order is placed on 6/30/2010, lead time to delivery is
>>> 60 calendar days, delivery would be on 8/28/2010. To do this I created a
>>> lead-time calendar that makes every day a work day by setting all days to
>>> 8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
>>> LeadTime is assigned to the task, no resources specified.
>>>
>>> The problem; project computes the Planned End Date at 8/22/2010 which by my
>>> calculation is 7 days short of 60. Changing the calendar attached to this
>>> task to the 24hour one increases the discrepancy.
>>>
>>> Any suggestions will of course be greatly appreciated.
>>>
>>> Steven Wheeler
>> .
>>
From: Roland on
Hi Steven,

Just curious. Why did you create another calendar just for lead-time? You
could use "edays" instead which would have given you the results needed
without additional calendar maintenance.

RC

"smw" wrote:

> I need to have a separate line item in my plan for the lead-times on several
> purchases. Example: order is placed on 6/30/2010, lead time to delivery is
> 60 calendar days, delivery would be on 8/28/2010. To do this I created a
> lead-time calendar that makes every day a work day by setting all days to
> 8:00 AM - 5:00 PM. Task is fixed duration, 60d, non-estimated, calendar
> LeadTime is assigned to the task, no resources specified.
>
> The problem; project computes the Planned End Date at 8/22/2010 which by my
> calculation is 7 days short of 60. Changing the calendar attached to this
> task to the 24hour one increases the discrepancy.
>
> Any suggestions will of course be greatly appreciated.
>
> Steven Wheeler
 |  Next  |  Last
Pages: 1 2
Prev: Project 2010
Next: OutlineGrandParent.duration