From: bcurley on 9 Feb 2009 02:49 Hi, With Project 2003 I used the "Analyze Timescaled Data in Excel" to export cumulative percent complete to excel over time. I haven't been able to get this with Project 2007 and I've looked at the Visual Reports and "Save As" to excel. Any suggestions on how to do this.
From: JulieS on 9 Feb 2009 12:34 Hello BCurly, I agree it's odd that the Cumulative Percent Complete field doesn't show in the field list picker but all is not lost. In Visual Reports, click the Save Data button and in the Save Reporting Data dialog box, select the Save Database button. That will save all data in the reporting DB including the Cumulative % Complete data. The MSP_EPMTaskByDay table contains the Cumulative Percent Complete data. I hope this helps. Julie Project MVP "bcurley" wrote: > Hi, > > With Project 2003 I used the "Analyze Timescaled Data in Excel" to export > cumulative percent complete to excel over time. I haven't been able to get > this with Project 2007 and I've looked at the Visual Reports and "Save As" to > excel. Any suggestions on how to do this.
|
Pages: 1 Prev: Error with tables Next: My Tasks View in Project 2007 server |