From: Roland on 27 May 2010 16:23 Project Summary usually contains the name of the initial project (automatically uses filename but can be changed). If you are using an existing schedule to build a new schedule, the value isn't automatically updated with the new name. To fix: type over the name with a new name "mapretty" wrote: > When I select the project summary task option, the value is "Safety > Register". This is not the name of my project. What is this, and how do I > get rid of it?
|