From: Christian W on
Hello all,

I have a problem with redistribution, i need to do that the redistribution
fill 8 hours day by day. But MSproject never do this.

For example,
If Bob had work (Task1) ...
BOB Day1 Day2 Day3 Day4
Task1 2 2 3 5

And now I have more work for BOB (Task2) and need to do this:

BOB Day1 Day2 Day3 Day4
Task1 2 2 3 5
Task2 6 6 5 3

But never do this!! how can do it ??

Have setting "redistribution resources" as follow

- "Manual"
- Search over... by "hours"
- "Redistribute complete project"
- Sort= "Priority, Standar"
- click 3 last items


Thanks in advance,
Christian W

From: JulieS on
Hello Christian,

I believe you are expecting the Resource Leveling command to do
something it never will. The resource leveling command --what you refer
to as redistribution -- only solves cases where the peak units for a
resource is above the maximum units set. When you assign resources to
tasks, you specify the assignment units, or Project may calculate them
for you based upon the task duration and the amount of work you enter.
So, if on task 1 you have Bob assigned at the hours below, Bob's
assignment units are as follows:

Day 1: 25%
Day 2: 25%
Day 3: 38%
Day 4: 63%

If you then assign Bob to Task 2 at 8 hours per day (100%), Bob is now
overallocated. If you use the resource leveling command, Project cannot
change the assignment unit for Task 2 to the remainder of Bob's maximum
unit. Your choices are either to ensure you do not assign Bob at above
37% to Task 2 (allowing 100% peak units on Day 4, but less than 100% on
Days 1-3, or go into the Resource Usage view and manually edit the work.

The other option is to ensure that Bob is always assigned at 100% (or
whatever his max. units are) and then use the resource leveling command
to spread the tasks out.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 1/28/2010 8:45 AM, Christian W wrote:
> Hello all,
>
> I have a problem with redistribution, i need to do that the redistribution
> fill 8 hours day by day. But MSproject never do this.
>
> For example,
> If Bob had work (Task1) ...
> BOB Day1 Day2 Day3 Day4
> Task1 2 2 3 5
>
> And now I have more work for BOB (Task2) and need to do this:
>
> BOB Day1 Day2 Day3 Day4
> Task1 2 2 3 5
> Task2 6 6 5 3
>
> But never do this!! how can do it ??
>
> Have setting "redistribution resources" as follow
>
> - "Manual"
> - Search over... by "hours"
> - "Redistribute complete project"
> - Sort= "Priority, Standar"
> - click 3 last items
>
>
> Thanks in advance,
> Christian W
>
From: Jan De Messemaeker on
Hi,

You are the victim of one of the very bad translations of Project terms
around.
As Julie describes, Leveling is not redistribution... but in some langages
(Dutch...) it is translated as the equivalent of redistribution.

Pity!

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
news:57CC9A12-6167-4CC4-AC66-AD459A16ABB0(a)microsoft.com...
> Hello all,
>

> I have a problem with redistribution, i need to do that the redistribution
> fill 8 hours day by day. But MSproject never do this.
>
> For example,
> If Bob had work (Task1) ...
> BOB Day1 Day2 Day3 Day4
> Task1 2 2 3 5
>
> And now I have more work for BOB (Task2) and need to do this:
>
> BOB Day1 Day2 Day3 Day4
> Task1 2 2 3 5
> Task2 6 6 5 3
>
> But never do this!! how can do it ??
>
> Have setting "redistribution resources" as follow
>
> - "Manual"
> - Search over... by "hours"
> - "Redistribute complete project"
> - Sort= "Priority, Standar"
> - click 3 last items
>
>
> Thanks in advance,
> Christian W
>


From: Christian W on
ok, i have project 2007 in spanish, where is "leveling" option ?

Thanks


"Jan De Messemaeker" wrote:

> Hi,
>
> You are the victim of one of the very bad translations of Project terms
> around.
> As Julie describes, Leveling is not redistribution... but in some langages
> (Dutch...) it is translated as the equivalent of redistribution.
>
> Pity!
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
> news:57CC9A12-6167-4CC4-AC66-AD459A16ABB0(a)microsoft.com...
> > Hello all,
> >
>
> > I have a problem with redistribution, i need to do that the redistribution
> > fill 8 hours day by day. But MSproject never do this.
> >
> > For example,
> > If Bob had work (Task1) ...
> > BOB Day1 Day2 Day3 Day4
> > Task1 2 2 3 5
> >
> > And now I have more work for BOB (Task2) and need to do this:
> >
> > BOB Day1 Day2 Day3 Day4
> > Task1 2 2 3 5
> > Task2 6 6 5 3
> >
> > But never do this!! how can do it ??
> >
> > Have setting "redistribution resources" as follow
> >
> > - "Manual"
> > - Search over... by "hours"
> > - "Redistribute complete project"
> > - Sort= "Priority, Standar"
> > - click 3 last items
> >
> >
> > Thanks in advance,
> > Christian W
> >
>
>
> .
>
From: Jan De Messemaeker on

Well, it is what you read as redistribution.
It does NOT redistribute, it only delays tasks. ONLY that. No redistribution
:-)
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availabliy check:
http://users.online.be/prom-ade/Calendar.pdf
"Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
news:ADBB69FE-40B4-4F8F-AED9-39FE7C705B2B(a)microsoft.com...
> ok, i have project 2007 in spanish, where is "leveling" option ?
>
> Thanks
>
>
> "Jan De Messemaeker" wrote:
>
>> Hi,
>>
>> You are the victim of one of the very bad translations of Project terms
>> around.
>> As Julie describes, Leveling is not redistribution... but in some
>> langages
>> (Dutch...) it is translated as the equivalent of redistribution.
>>
>> Pity!
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Christian W" <ChristianW(a)discussions.microsoft.com> wrote in message
>> news:57CC9A12-6167-4CC4-AC66-AD459A16ABB0(a)microsoft.com...
>> > Hello all,
>> >
>>
>> > I have a problem with redistribution, i need to do that the
>> > redistribution
>> > fill 8 hours day by day. But MSproject never do this.
>> >
>> > For example,
>> > If Bob had work (Task1) ...
>> > BOB Day1 Day2 Day3 Day4
>> > Task1 2 2 3 5
>> >
>> > And now I have more work for BOB (Task2) and need to do this:
>> >
>> > BOB Day1 Day2 Day3 Day4
>> > Task1 2 2 3 5
>> > Task2 6 6 5 3
>> >
>> > But never do this!! how can do it ??
>> >
>> > Have setting "redistribution resources" as follow
>> >
>> > - "Manual"
>> > - Search over... by "hours"
>> > - "Redistribute complete project"
>> > - Sort= "Priority, Standar"
>> > - click 3 last items
>> >
>> >
>> > Thanks in advance,
>> > Christian W
>> >
>>
>>
>> .
>>