From: JulieS on 14 Apr 2010 17:16 Hello Colleen, Sorry, no. Even if you change the display (Tools > Options, View tab) to only show date and not time, the time data will be exported to project. Even though *you* are not dealing with time, MS Project is. The best I can suggest is just to change the cell formats once the data is in Excel. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project On 4/14/2010 5:00 PM, Colleen wrote: > One of my managers says that when I send her the MSProject file and she > converts it to Excel that in addition to the start/finish dates, it puts in a > time in that field as well. For our project we are not dealing with time at > all, so all we need to know is the dates. She's been manually removing this > time from the field each week, but we are wondering if there is a way to > remove this time option so only dates appear in those columns? I look in the > project plan options and found an area to specify the working times, but when > I tried to delete both fields it would not allow me. It seems that a time > needs to be in both fields. Please confirm if there is a way to remove this > time stamp from the start/end date columns. Thanks! > > Colleen
|
Pages: 1 Prev: Current Date Next: Problem with copying and pasting tasks and keeping predecessors in |