From: Maanu on
I do not understand the point clearly. Can you make it clear?

"Jim Aksel" wrote:

> To make sure I understand, what this this does is gives the last milestone
> task a total slack of 0 days while increasing the slack of all other schedule
> tasks by 10 days (or an agreed amount).
>
> So, I would also alter tools/options/calculations and set "show tasks are
> critical when total slack" <10. I would then monitor the minumim value of
> total slack that is greater than 0. If the schedule is correct, I would
> have 1 task (the milestone) with total slack 0, all critical path tasks have
> total slack 10 days (it was 0) and then all other tasks are expected to have
> total slack greater than 10. So there should be a void with no tasks have
> less than 10 days total slack.
> --
> If this post was helpful, please consider rating it.
>
> Jim Aksel, MVP
>
> Check out my blog for more information:
> http://www.msprojectblog.com
>
>
>
> "Jan De Messemaeker" wrote:
>
> > Hi Manu,
> >
> > Simple.Add a task (0 days duration) with a Must Start On constraint 10 days
> > after the end of the final task. Show the Total Slack column: it shows your
> > buffer which will automatically adjust when tasks slip.
> >
> > Hope this helps,
> >
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> > +32 495 300 620
> > For availability check:
> > http://users.online.be/prom-ade/Calendar.pdf
> > "Maanu" <Maanu(a)discussions.microsoft.com> wrote in message
> > news:613595AC-2C5D-451C-87E6-483714B45931(a)microsoft.com...
> > > Hi,
> > >
> > > I need to add a buffer(10 days) at the end of the schedule to cover
> > > possible
> > > slippage. The buffer should decrease automatically with respect to the
> > > slippage. Is it possible to add such a buffer using microsoft project?
> > >
> > > Thanks!
> > >
> >
> >
> > .
> >
From: Jan De Messemaeker on
Hi,

I do not manage critical path (when tasks are critical the project is
generally already doomed) but Auto Filter always tells me which tasks have
the smallest buffer.

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Jim Aksel" <JimAksel(a)discussions.microsoft.com> wrote in message
news:51EBE99C-BADF-4C7F-BE60-E12C7FEDEFE2(a)microsoft.com...
> To make sure I understand, what this this does is gives the last milestone
> task a total slack of 0 days while increasing the slack of all other
> schedule
> tasks by 10 days (or an agreed amount).
>
> So, I would also alter tools/options/calculations and set "show tasks are
> critical when total slack" <10. I would then monitor the minumim value of
> total slack that is greater than 0. If the schedule is correct, I would
> have 1 task (the milestone) with total slack 0, all critical path tasks
> have
> total slack 10 days (it was 0) and then all other tasks are expected to
> have
> total slack greater than 10. So there should be a void with no tasks have
> less than 10 days total slack.
> --
> If this post was helpful, please consider rating it.
>
> Jim Aksel, MVP
>
> Check out my blog for more information:
> http://www.msprojectblog.com
>
>
>
> "Jan De Messemaeker" wrote:
>
>> Hi Manu,
>>
>> Simple.Add a task (0 days duration) with a Must Start On constraint 10
>> days
>> after the end of the final task. Show the Total Slack column: it shows
>> your
>> buffer which will automatically adjust when tasks slip.
>>
>> Hope this helps,
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Maanu" <Maanu(a)discussions.microsoft.com> wrote in message
>> news:613595AC-2C5D-451C-87E6-483714B45931(a)microsoft.com...
>> > Hi,
>> >
>> > I need to add a buffer(10 days) at the end of the schedule to cover
>> > possible
>> > slippage. The buffer should decrease automatically with respect to the
>> > slippage. Is it possible to add such a buffer using microsoft project?
>> >
>> > Thanks!
>> >
>>
>>
>> .
>>