From: Ana on 1 Jun 2010 06:48 Hello! 1. We have defined a resource type cost in the resource sheet 2. We have assigned its cost on a project task using Tools / Assign Resources 3. We started the project and at some point the project task containing this cost resource was completed. Problem: Although the task is completed, the cost of the resource type cost assigned to it does not appear in the actual cost. We are using MSP 2007. Thank you very much for your help explaining us why this happens. Regards, Ana
From: Dale Howard [MVP] on 1 Jun 2010 07:52 Ana -- To status an Expense Cost resource, you need to manually enter the actual expenditure in the Actual Cost column for that resource. Hope this helps. -- Dale A. Howard [MVP] VP of Educational Services msProjectExperts http://www.msprojectexperts.com http://www.projectserverexperts.com "We write the books on Project Server" "Ana" <Ana(a)discussions.microsoft.com> wrote in message news:DC2EC88C-3F54-4D67-AC98-BAF523F9E532(a)microsoft.com... > Hello! > > 1. We have defined a resource type cost in the resource sheet > 2. We have assigned its cost on a project task using Tools / Assign > Resources > 3. We started the project and at some point the project task containing > this > cost resource was completed. > > Problem: Although the task is completed, the cost of the resource type > cost > assigned to it does not appear in the actual cost. > > We are using MSP 2007. > Thank you very much for your help explaining us why this happens. > Regards, > Ana
From: john on 1 Jun 2010 07:56
On Jun 1, 3:48 pm, Ana <A...(a)discussions.microsoft.com> wrote: > Hello! > > 1. We have defined a resource type cost in the resource sheet > 2. We have assigned its cost on a project task using Tools / Assign Resources > 3. We started the project and at some point the project task containing this > cost resource was completed. > > Problem: Although the task is completed, the cost of the resource type cost > assigned to it does not appear in the actual cost. > > We are using MSP 2007. > Thank you very much for your help explaining us why this happens. > Regards, > Ana |