From: petra bäckström on 3 Jun 2010 04:24 I am getting a meassage in the resource sheet that sais "this resource should be levered based on a Day to Day setting"- what does that mean and what should i do? -- Petra
From: G�rard Ducouret on 3 Jun 2010 07:29 Petra, You probably assigned this resource on 2 tasks running in parallel. So you have to level the workload of that resource: Tools / Level resource... Hope this helps, G�rard Ducouret "petra b�ckstr�m" <petrabckstrm(a)discussions.microsoft.com> a �crit dans le message de news: F72B886E-0ED5-4C3F-BFFD-EED239626E98(a)microsoft.com... >I am getting a meassage in the resource sheet that sais "this resource >should > be levered based on a Day to Day setting"- what does that mean and what > should i do? > -- > Petra
|