From: Rob on
Hi,
Can I please ask somemore questions on this? This almost works but still shows completed work in the table to the right. Is there anyway of just showing the remaining work? Where is does show percentage complete, it does not just show whats remaining?

Thanks for any advice on this..


Regards,


-RW.



Andrew Lavinsky wrote:

Pull up the Resource Usage View.
26-May-10

Pull up the Resource Usage View. Go to Projects > Group By, and create a
new group to group by the following fields:

1) Resource
2) Project

Then add the fields required. That should get you close to what you are looking
for.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm