From: larry on 12 Nov 2009 11:48 If I have a regular gantt table view with multiple levels of indents, is there any way to save a customized view of select levels being shown? In other words, I might want only some level 2 tasks under certain summary activiteis, and then mabye leve 2 & 3 under others. Basically, what I'm looking for is something like a save current view Larry
From: Jim Spiller on 12 Nov 2009 11:58 Whether subtasks are expanded or collapsed is not something that can be saved with a view. Expanding and collapsing tasks is program wide. You can save your file with certain levels shown but if you expand/collapse summary tasks this will affect all (task) views. "larry" <larry(a)discussions.microsoft.com> wrote in message news:B965AC46-DE7F-499C-B656-1AF0A14F4027(a)microsoft.com... > If I have a regular gantt table view with multiple levels of indents, is > there any way to save a customized view of select levels being shown? In > other words, I might want only some level 2 tasks under certain summary > activiteis, and then mabye leve 2 & 3 under others. Basically, what I'm > looking for is something like a save current view > > Larry
From: larry on 12 Nov 2009 15:49 would really help and make a great enhancement, oh well, need to figure out a logical filtering system I guess "Jim Spiller" wrote: > Whether subtasks are expanded or collapsed is not something that can be > saved with a view. Expanding and collapsing tasks is program wide. You can > save your file with certain levels shown but if you expand/collapse summary > tasks this will affect all (task) views. > > > "larry" <larry(a)discussions.microsoft.com> wrote in message > news:B965AC46-DE7F-499C-B656-1AF0A14F4027(a)microsoft.com... > > If I have a regular gantt table view with multiple levels of indents, is > > there any way to save a customized view of select levels being shown? In > > other words, I might want only some level 2 tasks under certain summary > > activiteis, and then mabye leve 2 & 3 under others. Basically, what I'm > > looking for is something like a save current view > > > > Larry > > > . >
|
Pages: 1 Prev: Can I create a timeline of 'key dates' in Project? Next: Event ID 7882 |